Traffic infrastructure projects lag behind schedule

Construction on many traffic infrastructure projects is running behind schedule due to a slow land clearance process.

Traffic infrastructure projects lag behind schedule
Many traffic infrastructure projects in HCM City are behind schedule because of land clearance and resettlement problems. — Photo courtesy of baodautu.vn

The HCM City Management Board for Traffic Works Construction and Investment has requested an urgent meeting with the HCM City People’s Committee to discuss challenges with delayed projects.

Various traffic infrastructure construction works in the city have begun but have been delayed due to land clearance problems, the management board stated.

This has negatively affected the quality of life of locals living in the project area.

According to Đầu Tư (Investment) newspaper, HCM City currently has about 60 projects that are behind schedule due to land clearance.

Five of them are under a “red alert” status.

Specifically, the Long Kieng Bridge Construction Project, though approved by the city People’s Committee nearly 20 years ago, has only completed 52.6 per cent of the construction volume due to delays in land clearance. 

Last month, Nha Be District People’s Committee proposed purchasing 53 land lots to arrange resettlement for locals living in the land clearance area. The proposal is currently awaiting authorities’ approval.

Nam Ly Bridge Project, worth VND857 billion (US$37.2 million), encountered a similar circumstance. According to the initial plan three years ago, this project was supposed to be completed after one and a half years. However, only 39 per cent of the project, worth VND162 billion, has been completed.

The project investor is seeking the final land compensation unit price from the HCM City Land Valuation Council so that District 9 People’s Committee has a basis to carry out land compensation and then hand over the land plot to the investor.

Meanwhile, the Tang Long Bridge Project has had 30 per cent of its construction volume completed. This project has been halted for a year because 42 households have not settled on the land compensation price. 

Similar cases include the Xom Cui Bridge’s embankment project and Gia Dinh Park’s renovation project. Even though the Gia Dinh Park project has had 95 per cent of its volume completed, 12 households and one organisation have not handed their land over.

 

Administration hurdles

Problems related to land clearance are partly caused by ineffective coordination in resolving administrative procedures between consulting agencies, project management boards, and district-level people’s committees. 

Local residents' disagreement about land compensation prices has also contributed to the problem.

According to a representative of the HCM City Management Board for Traffic Works Construction and Investment, land clearance and compensation is the biggest obstacle when it comes to implementing traffic infrastructure projects.

“Compensation for site clearance usually makes up two thirds of the total investment of the project. However, disagreement on compensation rates between the state authorities and locals remains the biggest problem," the representative said.

In the time to come, the representative expects more proactive measures taken by HCM City authorities now that the Government has approved shortening the processing time for land compensation, resettlement and acquisition in the city.

A leader from a district-level People’s Committee said that land clearance is a very difficult task, especially when market land prices fluctuate rapidly and the process of setting up compensation plans and approving compensation prices is complicated.

As such, it is important to make fundamental changes in how land compensation and site clearance are carried out.

Recently, the HCM City People’s Committee assigned the Department of Natural Resources and Environment to be responsible for the implementation of land compensation and resettlement.

The department will also be in charge of issuing a coordination regulation among relevant authorities to ensure transparency, shorten the process of site clearance and compensation, and remove the administrative "knots".  VNS

HCM City’s transport infrastructure lags behind demand despite huge investment

HCM City’s transport infrastructure lags behind demand despite huge investment

HCM City allocates about US$431.9 million a year for the transport sector but the funding does not seem to be enough for narrowing the gap between the local infrastructure system and travel demand, heard at a meeting on June 10.

HCM City targets completion of many transport projects in 2020

HCM City targets completion of many transport projects in 2020

HCM City authorities are planning to complete or start key transport infrastructure projects this year in an aim to reduce traffic congestion and develop connections between the city and neighbouring provinces.

 
 

Other News

.
First 204,000 doses of AstraZeneca vaccine to be delivered in late February
First 204,000 doses of AstraZeneca vaccine to be delivered in late February
SOCIETYicon  18/02/2021 

The Drug Administration of Vietnam under the Ministry of Health has approved the import of the first 200,400 doses of AstraZeneca COVID-19 vaccine of the UK for emergency use.

18 news cases of Covid-19 reported in Hai Duong
18 news cases of Covid-19 reported in Hai Duong
SOCIETYicon  18/02/2021 

Chiều 18/2, Bộ Y tế công bố 18 ca mắc Covid-19 mới tại Hải Dương, nâng tổng số người mắc bệnh này trong cả nước lên 2347 trường hợp.

A strange year for foreigners to enjoy Tet in Vietnam amid COVID-19
A strange year for foreigners to enjoy Tet in Vietnam amid COVID-19
SOCIETYicon  18/02/2021 

The last year has seen several foreigners living in Vietnam experience unprecedented changes, particularly with 2020 being heavily affected by the COVID-19 pandemic, meaning that travelling between countries has become increasingly difficult.

18 new COVID-19 cases reported on Feb 17, all in Hai Duong
18 new COVID-19 cases reported on Feb 17, all in Hai Duong
SOCIETYicon  17/02/2021 

Vietnam saw 18 new locally-transmitted COVID-19 cases from 6am to 6pm on February 17, all in Hai Duong - the country's current largest hotbed, raising the national count to 2,329.

5-meter-tall apricot tree in Dong Nai attracts visitors
5-meter-tall apricot tree in Dong Nai attracts visitors
SOCIETYicon  18/02/2021 

Thousands of people have flocked to the southern province of Dong Nai these days to admire and take pictures with the giant apricot tree.

To prevent spread of Covid-19, students in nearly 40 provinces stay home after Tet
To prevent spread of Covid-19, students in nearly 40 provinces stay home after Tet
SOCIETYicon  17/02/2021 

Nearly 40 provinces and cities in the country have closed school until the end of February to prevent and control Covid-19.

Vietnam's third wave of Covid-19: when will it end?
Vietnam's third wave of Covid-19: when will it end?
FEATUREicon  18/02/2021 

VietNamNet would like to introduce an article by Prof. Nguyen Thien Nhan, Head of the HCM City National Assembly delegation.

Young families return to Hanoi after a long Tet holiday
Young families return to Hanoi after a long Tet holiday
SOCIETYicon  17/02/2021 

In the flow of people returning to Hanoi after the 7-day lunar New Year holiday (Tet), there were kids sitting behind their mothers on motorbikes, with countryside specialties tied behind the vehicles.

Crowded streets of Saigon on the first working day after Tet
Crowded streets of Saigon on the first working day after Tet
SOCIETYicon  17/02/2021 

On the first working day after the lunar New Year (Tet holiday), the streets of Saigon bustled again, but there were no traffic jams.

HCM City's airport gives COVID tests to passengers returning from north
HCM City's airport gives COVID tests to passengers returning from north
SOCIETYicon  17/02/2021 

HCM City’s authorities are testing arrivals from three major airports in the north (Noi Bai in Hanoi, Van Don in Quang Ninh province and Cat Bi in Hai Phong) as tens of thousands of passengers are returning after the Lunar New Year holiday.

Murals aim to protect environment
Murals aim to protect environment
SOCIETYicon  18/02/2021 

In Duc Thang ward in Hanoi’s Bac Tu Liem district there is a special mural depicting the Old Quarter and other important sites in the capital, created by members of the district’s Youth Union. 

Hanoi orders closure of streetside stalls, religious sites
Hanoi orders closure of streetside stalls, religious sites
SOCIETYicon  17/02/2021 

The capital city of Hanoi has ordered the closure of streetside stalls, monuments, temples and pagodas from February 16 to prevent the spread of COVID-19.

VIETNAM NEWS HEADLINES FEB. 18
VIETNAM NEWS HEADLINES FEB. 18
SOCIETYicon  18/02/2021 

No new COVID-19 cases found on February 18 morning

Farmers embrace livestreams, high-tech advances for better quality, productivity
Farmers embrace livestreams, high-tech advances for better quality, productivity
SOCIETYicon  17/02/2021 

Farmer Le Van Chin from the southern province of Long An recently livestreamed an advert about his cooperative’s red-flesh dragon fruit on his Facebook page.

Hanoi closes sidewalk eateries, cafés to curb COVID-19 spread
Hanoi closes sidewalk eateries, cafés to curb COVID-19 spread
SOCIETYicon  17/02/2021 

On February 16, Hanoi's competent forces were down the street to check vendors’ obedience to COVID-19 epidemic preventive regulations.

40 cases of Covid-19 reported in three provinces
40 cases of Covid-19 reported in three provinces
SOCIETYicon  16/02/2021 

On the afternoon of February 16, Vietnam reported 40 new cases of Covid-19, bringing the total number to 2,311.

Two COVID-19 cases reported early February 16
Two COVID-19 cases reported early February 16
SOCIETYicon  16/02/2021 

Two cases of COVID-19 were detected in the past 12 hours to 6am February 16, raising the national count to 2,271, of which 1,372 were locally transmitted, according to the National Steering Committee for COVID-19 Prevenon and Control.

Youngsters optimistic about Vietnam’s outlook over next 15 years
Youngsters optimistic about Vietnam’s outlook over next 15 years
SOCIETYicon  16/02/2021 

Some 72 percent of 1,200 Vietnamese youngsters and adolescents said they believe that in the next 15 years things will get better than they were before 2019, 

Traffic accidents kill 19, injure 24 on fourth day of Lunar New Year
Traffic accidents kill 19, injure 24 on fourth day of Lunar New Year
SOCIETYicon  15/02/2021 

As many as 31 road traffic accidents were recorded on February 15, or the fourth day of the Lunar New Year

40 new COVID-19 cases confirmed on Monday evening
40 new COVID-19 cases confirmed on Monday evening
SOCIETYicon  15/02/2021 

Forty new community COVID-19 cases were detected on Monday, including two in Hanoi.

 
 
 
Leave your comment on an article

OR QUICK LOGIN