Delayed BOT projects threaten to disrupt future power supply

A series of build-operate-transfer power projects are lagging behind set schedules by as much as a year due to the global pandemic, threading concern into the power supply issue in the coming time.

1495p10 delayed bot projects threaten to disrupt future power supply
Delayed BOT projects threaten to disrupt future power supply

A build-operate-transfer (BOT) power developer who declined to be named told VIR that his venture is facing delays of more than six months due to supply chain disruptions, unavailability of manpower, and issues in obtaining project financing due to the coronavirus.

“Our project is under negotiation and has not started construction. The recent lockdown and movement restrictions imposed to control the spread of COVID-19 have contributed to our delay,” the developer said. “The longer the project is delayed, the harder it is for our project as lenders have started to restrict or phase out financial support, even though we committed to using the most advanced technology.”

Meanwhile, South Korean national power company Korea Electric Power Corporation’s (KEPCO) poor track record was noted by the director of Energy Finance Studies Asia and author of the report “Question Time for KEPCO’s Board” as it witnessed poor performance, also due to the pandemic. Its share price shot down 22.8 per cent year-to-date, creating questions for their overseas investment and BOT power activities in Vietnam, including the 1,200MW Nghi Son and the potential 1,200MW Vung Ang 2.

Over the past few decades, there has been a craving for public-private partnership in the development of large-scale energy and infrastructure ventures across Vietnam. However, along with the revised Power Development Plan VII (PDP7) that has not been implemented as expected, the BOT power sector has moved slowly, with long preparation times. There are currently 15 BOT power projects, including three projects on track (in particular, Vinh Tan 1 started power generation six months earlier than planned) and others being delayed or are unidentified due to certain obstacles in negotiation (see chart).

For instance, the 1,200MW Hai Duong BOT power plant in the northern province of Hai Duong, licensed in 2011, remains under construction through a joint-venture between Malaysia’s Jaks Resources and China Power Engineering Consulting Group. As per the initial plan, this power project was expected to start commercial operations in 2016 with the first turbine and in 2017 for the second.

Hai Duong, where the project is located, has already requested the prime minister and relevant authorities several times to urge the foreign investors to implement construction on schedule as previously committed. The province also asked the prime minister to issue measures for the continuous delay for many times.

Industry insiders said that financial arrangements are not a straightforward assignment for power projects that require huge capital and must take environmental concerns into account. Looking back on the progress since the release of BOT bidding documents of Nghi Son 2 in the central province of Thanh Hoa, it took about 10 years for the thermal power initiative to complete all procedures in order to reach financial closure. BOT Nghi Son 2 is invested by a consortium consisting of Japan’s Marubeni Corporation and KEPCO. The $2.79 billion project started construction in 2018 and was expected to be completed next month.

Some other BOT schemes under negotiation include India’s Tata Power for Long Phu 2, Thailand’s EGAT Quang Tri 1, and Toyo Ink’s Song Hau 2.

The Ministry of Industry and Trade (MoIT) admitted in a document, “The negotiation of BOT contracts and investment licence issuance take time due to the complex involvement of many related ministries. Obstacles have been mainly incentive policies, foreign exchange, early termination of contract, and more. It usually takes a long time for other authorised agencies to review and provide comments. The MoIT is not able to take control of contract negotiation and signing. BOT plants such as Vung Ang 2, Vinh Tan 3, Long Phu 2, and Song Hau 2 are facing such problems.”

 

Last year, a representative of the BOT Van Phong 1 thermal power investor told VIR that the delay in the implementation of BOT projects in the industry “is due to the terms of related contracts, electricity trading, land lease, and government guarantee,” adding that it takes time to negotiate to ensure the ability to arrange financing from foreign credit institutions.

Earlier this year, the MoIT released its latest report on the implementation of power projects in the revised PDP7. Some 47 of the 62 approved plants are behind schedule to various degrees, ranging from a few months to as long as five years. Delays in many power projects in particular threaten shortages in the coming time.

The total capacity of all power sources likely to be operationalised over the course of 15 years (2016-2030) is expected to reach about 80,500MW, over 15,200MW less than the figure forecast in the revised PDP7 for 2011-2020 with a vision towards 2030.

Vietnam is currently reviewing and building an eighth PDP. The prime minister also urged the MoIT and related agencies to take measures to promote key power projects and recommend solutions for power projects that are falling behind schedule.

The MoIT also reported that relevant agencies have to prepare carefully to minimise power outages across the country, especially in the southern region. In some cases, it is required to mobilise electricity that is generated by oil and diesel as well as raise the awareness of energy conservation among residents. Many solar power plants, meanwhile, are also expected to be soon put into operation, which will also contribute to address the shortages.

Under Directive No.20/CT-TTg released last month on saving electricity during 2020-2025, the prime minister has called on the whole country to save at least 2 per cent of total power consumption each year.

Administrative agencies must work with electricity suppliers to save 5 per cent of total consumption each year. Public lighting operators were required to save 20 per cent of total electricity consumption during the period. Power-saving technology must be used in public lighting.

Hospitality providers, office centres, and apartment buildings were asked to cut 50 per cent of outdoor advertising lighting capacity at night.

Households are being asked to use equipment with energy-saving labels, economically and effectively use power, and install solar panels on roofs where possible. VIR

Nguyen Thu

Nearly US$3 billion worth of loans to BOT projects likely to become bad debt

Nearly US$3 billion worth of loans to BOT projects likely to become bad debt

Forty-nine BOT (build-operate-transfer) transport projects have been reported as having revenue below expectations.

Transport Ministry proposes State to compensate controversial BOT tollgates

Transport Ministry proposes State to compensate controversial BOT tollgates

The Ministry of Transport has proposed that the Government compensate developers of two out of four build-operate-transfer (BOT) tollgates and shut them down due to protests among road users.

 
 

Other News

.
Many hoteliers intend to divest capital due to heavy losses
Many hoteliers intend to divest capital due to heavy losses
BUSINESSicon  16/10/2020 

Over the past eight months, hotel room tariffs have plunged and hotel room occupancy rates have remained low, forcing several hoteliers to divest capital with many financially weak hotels in the local market being put up for sale.

Thai billionaire, European brewer lose money in Sabeco investment deal
Thai billionaire, European brewer lose money in Sabeco investment deal
BUSINESSicon  16/10/2020 

The Sabeco price has seen a strong recovery in the last half a year, but is still at a low price. Both Thai billionaire and the big brewer Heineken have lost money because of the drop in Sabeco share price.

Salary increases in 2020 lowest in 10 years: survey
Salary increases in 2020 lowest in 10 years: survey
BUSINESSicon  16/10/2020 

Salaries increased by 6.5% this year at multinational companies (MNCs) and 5.2% at Vietnamese companies, and are forecast to increase by 7 per cent and 7.7% next year, according to the Talentnet – Mercer Total Remuneration Survey.

State firms more resilient than foreign, Vietnamese private companies: survey
State firms more resilient than foreign, Vietnamese private companies: survey
BUSINESSicon  15/10/2020 

Business resilience is highly correlated with level of digitisation, the Business Pandemic Resilience Diagnostic conducted by Grant Thornton...

Pandemic a test of fire for Vietnamese enterprises
Pandemic a test of fire for Vietnamese enterprises
BUSINESSicon  15/10/2020 

The COVID-19 pandemic has been a test for Vietnamese businesses as many have been and will be struggling to recover for the foreseeable future. 

Five expy projects unlikely to attract private investors
Five expy projects unlikely to attract private investors
BUSINESSicon  15/10/2020 

Although the National Assembly Standing Committee has given its approval to switch three of the eight subprojects of the North-South Expressway from the public-private partnership (PPP) format into wholly State-invested, 

Only 5% FDI projects in Vietnam use high technologies
Only 5% FDI projects in Vietnam use high technologies
BUSINESSicon  15/10/2020 

Vietnam is home to 32,539 valid foreign direct investment (FDI) projects with registered capital of a combined US$381 billion, of which US$233 billion has been fully disbursed.

The Vietnamese brain will decide
The Vietnamese brain will decide
FEATUREicon  16/10/2020 

"Vietnamese have nothing but brains to develop the country in the future." 

Stable outlook expected for Vietnamese dong
Stable outlook expected for Vietnamese dong
BUSINESSicon  16/10/2020 

While Vietnam is at risk of being listed as currency manipulator by the US, such a risk appears low, as the US will likely continue to reduce its dependence on Chinese exports by reorganizing its supply chain with other partners.

Vietnam banking sector to suffer in 2020 before rebounding in 2021
Vietnam banking sector to suffer in 2020 before rebounding in 2021
BUSINESSicon  15/10/2020 

Fitch Solutions expected credit growth to weaken to 7% in 2020 from 13.7% in 2019, but the growth is predicted to pick up to 12% one year later.

Realising revised growth ambitions
Realising revised growth ambitions
BUSINESSicon  15/10/2020 

Vietnam’s fourthquarter economic outlook is brighter on the back of a rise in domestic consumption and public investment.

Businesses line up for further support
Businesses line up for further support
BUSINESSicon  15/10/2020 

Continued facing with massive woes, the business community in Vietnam is in dire need of the government’s assistance for investors and enterprises to struggle through the global health crisis and grabbing new business

Infrastructure development at the centre of PPP decree direction
Infrastructure development at the centre of PPP decree direction
BUSINESSicon  16/10/2020 

Further clarifying the legal framework for infrastructure development via wider participation of private investors is expected to help the country attract more funding into the industry.

Gov’t support aids automobile industry
Gov’t support aids automobile industry
BUSINESSicon  14/10/2020 

The domestic automobile industry was forecast to thrive, given the Government’s supports in tax policies for imported automobile components coupled with the increasing income of citizens.

Digital economy and fintech see growth amid COVID-19
Digital economy and fintech see growth amid COVID-19
BUSINESSicon  15/10/2020 

The Prime Minister’s Economic Advisory Group met with the local fintech firm MoMo in HCM City on Monday.

Vietnam Airlines reports huge losses
Vietnam Airlines reports huge losses
BUSINESSicon  14/10/2020 

Vietnam Airlines Group, listed as HVN on the HCM Stock Exchange, earned nearly VND24 trillion (US$1.04 billion) in total consolidated revenue in the first nine months of this year, marking an estimated loss of VND10.75 trillion, 

Vietnam to increase imports of coal and gas
Vietnam to increase imports of coal and gas
BUSINESSicon  14/10/2020 

The latest data from the ministry sent to the National Assembly shows that Viet Nam is transitioning from an energy exporter to a net importer.

Coastal developers prepare for good upcoming times
Coastal developers prepare for good upcoming times
BUSINESSicon  14/10/2020 

In anticipation for the world eventually opening back up for travellers, developers are exploring the high potential of Vietnam’s world-renowned coastal urban areas.

Tax relief should not be “One size fits all”
Tax relief should not be “One size fits all”
BUSINESSicon  14/10/2020 

The Private Economic Development Research Board, under the Advisory Council for Administrative Procedure Reform, has proposed a 30% reduction in corporate income tax for all businesses this year.

Big investors pour money into IZ projects as land fund declines
Big investors pour money into IZ projects as land fund declines
BUSINESSicon  15/10/2020 

The land rent in some industrial zones in Hai Phong, Bac Ninh and Hai Duong has increased by 20-30 percent.

 
 
 
Leave your comment on an article

OR QUICK LOGIN