VietNamNet Bridge – Hanoi’s Cat Linh – Ha Dong elevated railway is set to launch after a testing phase lasting between three to six months.

{keywords}

The Cat Linh - Ha Dong elevated train undergoes a trial through Hoang Cau Bridge in Dong Da Disstrict. — VNA/VNS Photo Huy Hung


The trial will commence on September 20, deputy director of the Ministry of Transport’s Railway Project Management Board Vu Hong Phuong told the project review meeting on Thursday.

“Considering similar urban railway projects around the world, the trial period normally lasts from three to six months,” he said.

On the occasion, Phuong reported that the Chinese contractor has been slow in completing the project and finalising the detailed test plan, maintenance procedures and system safety dossiers, which might influence the project handover.

At the meeting, transport officials expressed their concern about payments made to 681 workers who will be involved in operating the train during the trial period. A total of VND116.5 billion (nearly $5 million) had been paid for providing theoretical and practical training for the workers in China and Vietnam.

Minister of Transport Nguyen Van The has asked deputy minister Nguyen Ngoc Dong to work with the city authority, investors and relevant agencies to solve existing problems.

As much as 96 per cent of the project’s installation and construction work has been completed, the online newspaper Vietnamplus reported.

Since August 1, the railway has been connected to the national power grid for trial operation.

Connecting Dong Da District’s Cat Linh Street with Ha Dong District’s Yen Nghia bus station, the 13km-long elevated railway includes 12 stations and a depot at Phu Luong Ward in Ha Dong District. The railway will operate 13 trains with four carriages each running every two minutes at speeds of 35 to 80kmph.

The railway has been constructed using Official Development Assistance (ODA) from China with a total investment of US$868 million.

Source: VNS

related news