A worker cleans a train on the North-South line. 

 

 



The Ministry of Planning and Investment (MPI) filed a report to Prime Minister Nguyen Xuan Phuc on the railway project, showing its approval for the lower-cost option instead of the Ministry of Transport (MoT) plan.

Citing analysis by experts from Germany and the Netherlands, the ministry said that with the span of thousands of kilometres, a running speed of 200km/h would be effective and help save some 32 billion USD compared to MoT’s solution.

Travelling between Hanoi and Ho Chi Minh City, under the MPI plan, would take about eight hours.

Moreover, if factors besides direction and length are taken into consideration, the cost may be further reduced.

Deputy Minister of Planningand Investment Vu Dai Thang said the ultimate solution was to upgrade the oldinfrastructure for freight and simultaneously develop a new project to carrypassengers.

Previously, MoTproposed a plan to upgrade the current North-South railway to transport local commuters and commodities. Meanwhile, a new high-speed system which would allow a train to run at 320km/h would be built with the tentative investment of about 58.7 billion USD over 30 years from 2020 to 2050.

The project will beimplemented under the Public-Private Partnership (PPP) model, with 80 percentof the investment allocated from the State budget and the rest funded by theprivate sector.

According to MPI,after completing the project’s first phase connecting Hanoi with Vinh inNghe An province and Nha Trang in Khanh Hoa province with HCM City in2032, these two routes will be able to carry 364,000 passengers a day. The total number of daily passengers on both routes, however, is predicted to reach just 55,000 to 58,000, only 16 percent of the capacity.

Therefore, MPI saidit would be more effective and cost-effective to have the system perform at theslower speed of 200km/h.

Technology is another concern in the project. MPI warned against depending on foreign partners to operate the system and asked MoT to accelerate multilateral cooperation to reduce expenditure and encourage the private sector’s participation.

“The North-Southhigh-speed railway will be operated through generations; therefore, it isessential to have solutions for technology transition. It will be costly to buy new technology whenever the old one is out of work,” said Deputy Minister Thang.

According to Dr. Tran Dinh Thien, former Director of the Vietnam Institute of Economics, the project’s investment efficiency must be considered. The high investment could result in expensive tickets, making it hard to compete against budget flights.-VNA

Hyundai wants to invest in North-South express railway

Hyundai wants to invest in North-South express railway

South Korea’s Hyundai Group wants to provide a comprehensive solution for the North-South express railway project, including planning, funding, construction, operation and maintenance.

North-south express railway project attracts foreign contractor interest

North-south express railway project attracts foreign contractor interest

The representative of the Project Management Unit No 2 under MOT said many foreign investors from France, Japan and South Korea have expressed interest in the Highway 45-Nghi Son section of the north-south expressway project.