Dong Nai urged to hand over ‘clean land’ for Long Thanh Airport

Dong Nai plans to send officials to assist the Long Thanh District in speeding up site clearance, compensation and resettlement for households affected by the Long Thanh airport project  so that construction can begin next year. 

 

{keywords}
A rendering of the proposed Long Thanh International Airport in the southern province of Dong Nai. Photo courtesy of Airports Corporation of Vietnam 

As scheduled, Dong Nai Province will hand over the priority area of ​​1,800ha to the project investor by October, and the entire land by the second quarter of 2021.

Cao Tien Dung, chairman of the provincial People’s Committee, said at a recent meeting that it was important to complete the assessment of cleared land for affected households within this year.

As of today, Long Thanh District People’s Committee has made three compensation payments worth over VND440 billion (US$19.08 million) to 269 households, according to Dung.

Le Van Tiep, vice chairman of Long Thanh District People’s Committee, said due to the large number of affected households with the large land area, compensation payments will be implemented several times. 

At the end of April, the provincial People’s Committee started construction of five bidding packages to build technical infrastructure at the Loc An - Binh Son resettlement area, including four roads and drainage systems.

Land used for resettlement purpose is expected to be handed over to the affected households next month when the roads are completed. Meanwhile, the remaining technical infrastructure facilities are being implemented quickly, according to Tiep. 

Delayed disbursement

According to the Ministry of Planning and Investment, delayed land acquisition disbursement for the airport could affect the progress of the airport, scheduled to begin in the second quarter next year and to be completed by 2025.

As of June, only 10 per cent of the VND18.19 trillion ($784 million) allocated for airport land acquisition and compensation had been disbursed, according to the ministry.

In April, the Dong Nai administration committed to disburse all funding within this year, but the low disbursement rate means the province will likely fail to complete land acquisition and compensation by 2021 as promised, experts have warned.

Recently, Prime Minister Nguyen Xuan Phuc requested the province to speed up site clearance and compensation as well as disbursement of all VND23 trillion for the airport project in accordance with the law.

The PM also set a deadline for assessment of cleared land for compensation purposes by the end of November.

He suggested that the Ministry of Transport closely work with Dong Nai Province to promptly solve any hurdles to ensure the project remains on schedule.

To build Long Thanh airport, the site clearance project must acquire more than 5,000ha of land and more than 364 extra hectares to build two resettlement sites.

Around 4,800 local households and 26 organisations are expected to be relocated to make way for the proposed airport. 

The airport is expected to serve 100 million passengers and five million tonnes of freight each year.

Covering a total area of more than 5,580 hectares, the airport will be located in six communes in Long Thanh District in Dong Nai Province. The airport’s total investment is VND336.63 trillion ($14.47 billion), with construction divided into three phases.

In the first phase, a runway and one passenger terminal along with other supporting works will be built to serve 25 million passengers and 1.2 million tonnes of cargo each year.  VNS

Long Thanh airport project may lag behind schedule

Long Thanh airport project may lag behind schedule

The Ministry of Planning and Investment has expressed concern that the Long Thanh airport project might not get off ground in 2021 as scheduled, as the disbursement of capital for site clearance works has met a mere 10% of the target.  

Compensation rates approved for lands to be acquired for Long Thanh airport

Compensation rates approved for lands to be acquired for Long Thanh airport

Dong Nai Province authorities have approved the compensation rates payable to households who have to move to make way for the long-awaited Long Thanh international airport. 

MORE NEWS

Ministry announces 218 firms as prestigious exporters of Vietnam

As many as 218 companies have won the “Prestigious Export Business” title for 2021, according to the list unveiled by the Ministry of Industry and Trade (MoIT) on December 5.

Vietnam, RoK agree to upgrade ties to comprehensive strategic partnership

Vietnam and the Republic of Korea (RoK) have agreed to upgrade their ties to a comprehensive strategic partnership, President Nguyen Xuan Phuc told the press following his talks with RoK President Yoon Suk-yeol in Seoul on December 5.

Tourists flock to Sa Pa to see clouds

The number of tourists to Sapa (Lao Cai Province) has rocketed in recent days to admire the amazing clouds.

Fried squid paste in Halong Bay

As one of the largest seafood regions in Vietnam, Quang Ninh has the tastiest seafood dishes that one cannot forget. Among them, fried squid paste in Halong Bay will leave a lasting impression on diners thanks to its unforgettable taste.

Experience Hanoi in its autumn glory

Thanks to its geographical location, the Vietnamese capital city of Hanoi witnesses contrastingly different weather conditions during the four seasons of the year.

VIETNAM NEWS HEADLINES DECEMBER 5

HCYU’s 7th National Congress to be held next week

Korean President hosts State-level welcoming ceremony for Vietnamese counterpart

President Nguyen Xuan Phuc was welcomed in Seoul with a 21-gun salute which is given to a foreign head of state during a State-level visit to the Republic of Korea (RoK).

VIETNAM BUSINESS NEWS DECEMBER 5

2022 ASEAN Postal Business Meeting to be held in Binh Dinh

Ministry considering EVN’s proposal for electricity price hikes

The Ministry of Industry and Trade is reviewing Vietnam Electricity's (EVN) proposal to increase electricity prices as rising input cost was weighing on the largest power company with record loss anticipated for this year.

Proper investment needed to develop night-time economy in Vietnam

The night-time economy of major cities in the country has remained underdeveloped due to a lack of proper investment and an absence of a legal framework and policies to promote it, authorities said.

Vietnam's rice exports likely to reach US$3.5 billion this year

Vietnam is anticipated to rake in roughly US$3.5 billion from exporting more than seven million tonnes of rice this year, according to industry insiders.

Local movie to be screened at Australian Vietnamese Film Festival

Vietnamese film "Cô gái từ quá khứ" (Girl from the past) will be introduced at the Australian Vietnamese Film Festival (AVFF) 2022 which is getting underway in Melbourne, Australia.

Auctions for car licence plates to be tested from July 2023

The starting price of a car licence plate put up for auction is VND40 million. The price may increase by increments of VND5 million.

Purpose-led business to drive superior performance

Working and developing a career at an enterprise with a mission towards sustainable development, employees can bring their goals to life.

Vietnam is well-positioned for green hydrogen production

Green hydrogen (GH2) industrial development is a direction for Viet Nam in the energy transition roadmap to achieve the goal of zero carbon emissions by 2050 but challenges remain, experts said.
back_to_top