In pictures: Water gushes from hydropower dam’s cracks
Hydro-power barrage cracked, locals worried

Mr. Dung also said that there were errors in design inspection and consulting-supervision. Moreover, the work is during the two-year period of warranty but the contractor did not work closely with the investor to fix errors.
Experts said that the volume of water leaked through the dam (30l per second) is quite high. They asked the contractor to check the entire dam and fill all cracks with cement, asphalt, etc.
Meanwhile, in the morning of March 21, the investor of Song Tranh 2 hydro-power told Quang Nam authorities that water leaked through the dam because the drainage pipe was stuck.
Quang Nam province’s Party Chief Nguyen Duc Hai stressed that the most important task is calming local people down. He asked all competent agencies to solve the incident thoroughly to ensure safety for people in the downstream region.
Deputy PM Hoang Trung Hai has instructed the Ministry of Industry and Trade, the Electricity of Vietnam Group (EVN) and the State Council for Checking and Taking over Construction Works to urgently inspect and fixed errors at Song Tranh 2 hydropower plant.
Nam Nguyen