Land compensation to be paid this year for Long Thanh Airport: official

Chairman of the Dong Nai People’s Committee Cao Tien Dung speaks about the 1,800ha of land that will be made available for the construction of Long Thanh Airport in October

Workers cut down rubber trees in a plantation located within an area marked for the construction of Long Thanh International Airport in Dong Nai. 

 

What are Dong Nai authorities doing to ensure land clearance for the first phase of construction for Long Thanh Airport is completed by October?

Right now we are in the process of settling land clearance and compensation for households having to relocate for Long Thanh Airport. We’re confident that more than 1,800ha of clean land will be ready for the first phase of the airport's construction by late October as we promised to the Government.

The most challenging task for us right now is finding places to live for the people who have had their land claimed for the construction of the airport because the number is quite a lot. Dong Nai is making advance payments and urging the households to find places to temporarily move to, to make room for the project. In the days ahead, we planned to hold a random number picking for these households to decide the locations for their new homes in the Loc An-Bình Son resettlement area. According to our plan, by late October, 1,800ha of clean land for the construction of the Long Thanh Airport will be available for the project.

Of the 1,800ha that Dong Nai authorities will have to hand over for the airport authority in October, more than 630ha belong to local households. Long Thanh District People’s Committee has already paid more than VNĐ900 billion ($38 million) in compensation to 456 households who have had their land revoked for the construction of the airport.

There is a big rubber plantation on that land. How will that be dealt with?

A plan for clearing the rubber plantation has already been decided. However, the current pandemic has delayed the progress of cutting down of the trees, due to lower number of exports resulting in less demands. Still, we believe that by late October we’ll have cleared the land for the Long Thanh Airport project, because after all, the cutting down of the trees is easier than calculating compensation lands for hundreds of households.

How about the settlement of the remaining 3,000ha for the airport?

According to the plan, compensation for the remaining 3,000ha will be completed by late November. In other words, within December this year, the entire 5,000ha will be available for the construction of the airport.

In the meantime, we’ve focused our investment on the construction of the Loc An-Bình Son resettlement area for people who have been relocated to make way for the airport.

Does this mean that Dong Nai authorities will complete their compensation plans for families affected by the construction of Long Thanh Airport by late 2020?

Yes! Compensation will be completed by late 2020. We hope that compensation matters will be completed within this year and next year, we will need to worry about clearing the ground to make way for construction.

We’re well aware that if compensation is delayed to next year, we will need to deal with changes to land prices set in 2021 as well, which will likely result in disputes and complaints given there are two compensation schemes applied for different households within a single project. — VNS

Delay in land disbursement stymies progress of Long Thanh int'l airport

Delay in land disbursement stymies progress of Long Thanh int'l airport

A delay in land acquisition disbursement for the proposed Long Thanh international airport in the southern province of Dong Nai could affect its progress, experts have warned.

Dong Nai urged to hand over ‘clean land’ for Long Thanh Airport

Dong Nai urged to hand over ‘clean land’ for Long Thanh Airport

Dong Nai plans to send officials to assist the Long Thanh District in speeding up site clearance, compensation and resettlement for households affected by the Long Thanh airport project  so that construction can begin next year. 

MORE NEWS

More foreign visitors to HCMC signals thriving tourist season

Roughly 100 French, American, German tourists traveled to Ho Chi Minh City on French Le Laperouse yacht of Ponant after the last visit in mid-November 2019 signaling a thriving tourist season.

First monkeypox infection detected in HCM City

The Ho Chi Minh City Department of Health has just announced the first reported case of monkeypox in Vietnam.

VIETNAM BUSINESS NEWS OCTOBER 3

2.97 billion USD in FDI poured into HCM City in 9 months

Trendy jobs in Vietnam

New and fashionable professions are being pursued by many young people. But not everyone is succeeding.

Shooting star targets bright future

After the retirement of senior champions, the Vietnam shooting team is now relying on its younger athletes, such as 18-year-old Phi Thanh Thao, who was recently nominated as Best Young Athlete of 2022 at the prestigious Victory Cup.

Hanoi needs world-class entertainment sites to lure tourists

According to experts, the lack of world-class amusement and entertainment zones is a big "hole" in Hanoi's tourism.

HCM City tightens management of food labelled 'organic'

Many families choose organic food though recently several supermarkets and e-commerce platforms had to apologise to consumers after non-organic food was labelled and sold as organic.

Vietnam win ticket to 2022 Futsal Asian Cup quarterfinals

Despite their defeat in the match against Japan on October 2, Vietnam’s national futsal team will advance to the quarterfinals in the 2022 Futsal Asian Cup as it ranked second in Group D.

Many parts of Vietnam saw increased fertility rates during pandemic

Fertility rates over the past two years increased across many localities in Vietnam, and it was even higher than the total replacement birth rate, said Director General of the General Department of Population and Family Planning Nguyen Doan Tu.

HCMC plans to eliminate 20,000 slum areas by 2025

According to the Ho Chi Minh City Department of Construction, over the past 20 years, the city has removed 36,000 slum areas along canals, but there are still about 20,000 of them.

Vietnam to have 33 new highways by 2030

With 33 highway projects totaling nearly 3,000 km long planned for construction in 2021-2030, a decade of busy expressway building is expected.

Viettel, VNPT lead Vietnam’s Top 10 most valuable brands

Four telecommunications brands of Vietnam have a total value of 13,136 million USD.

Floods kill eight in Nghe An, Ha Tinh

Heavy downpours and floods in the north central region claimed the lives of eight people in Nghe An and Ha Tinh provinces as of 5:30pm on October 2.

Localities urged to rectify flaws in fishery sector

With the visit of the European Commission’s delegations ahead, Vietnam’s ports and fishers are aiming to remedy the previously criticised issues regarding international fishing regulations.

Market likely to continue to correct this week

Analysts said that in the current environment, financial markets will be very likely to continue revaluing.
back_to_top