return icon Vietnamnet.vn

Lessons learned from urban railway projects

The urban railway projects that have been and are under construction are all behind schedule, so the total investment must be adjusted.

This is a lesson learned for the implementation of future projects.

According to the Ministry of Transport, Hanoi and Ho Chi Minh City have six urban railway line projects. Hanoi has four routes, including Cat Linh - Ha Dong, Nhon - Hanoi station, Nam Thang Long - Tran Hung Dao, Yen Vien - Ngoc Hoi and Ho Chi Minh City has two routes, including Ben Thanh - Suoi Tien and Ben Thanh - Tham Luong. These projects are in the same situation of being implemented slowly while the investment increases.

The Nhon-Hanoi station urban railway project started in 2010 and it has missed deadlines several times. As a result, the total investment increased from VND21,912 billion to VND32,910 billion, up by more than VND 10,998 billion from the initial capital.

In Ho Chi Minh City, the Ben Thanh - Suoi Tien project started in 2012 and its deadline has been extended many times. The goal of operation in 2022 failed as progress has only reached 91%. The capital also increased from VND 17,387 billion to VND 43,757 billion, up by VND 26,370 billion.

The Yen Vien - Ngoc Hoi urban railway project in Hanoi was approved by the Ministry of Transport in 2008, and was expected to be completed in 2017, but the construction has not started. The investment capital is estimated to increase from VND 19,046 billion to VND 65,175 billion.

The Nam Thang Long - Tran Hung Dao urban railway project in Hanoi was approved in 2008, and scheduled for completion in 2015, but it has not yet started. The total investment is estimated to increase from VND 19,555 billion at the beginning to VND 35,679 billion.

The Ben Thanh - Tham Luong urban railway project in HCM City was approved in 2010, and planned for completion in 2018, but has been delayed to 2026. The total investment is expected to increase from VND 26,116 billion to VND 47,890 billion.

Slow progress

There are many reasons for the slow progress of urban railway projects, but slow site clearance is the main one.

For the Nhon - Hanoi station project, because of problems with site clearance, the contractor could not do their job. For this reason, the contractor asked the investor for compensation of US$114 million.

The Cat Linh - Ha Dong urban railway project also had to adjust the schedule and design because of a lack of space to build a two-story station. The investor had to adjust the design of the station from 2 to 3 floors.

In addition, the design of some urban railway projects did not fit with the actual planned area, which led to many difficulties in implementation.

For example, the Nhon - Hanoi station railway project (12.5 km long) has 4km underground route. However, the underground passage is entangled with the foundation of construction works.

Deputy Transport Minister Nguyen Ngoc Dong said that for future urban railway projects, it is necessary to separate site clearance into a single project, which must be implemented first. Once site clearance is complete, project implementation will be ensured and help minimize the increase of capital investment.

Mastering technology, understanding technical standards is also a must.

Urban railway technical standards are very new to Vietnam and the current projects are all invested in by foreign loans. Therefore, when signing loan agreements, it is necessary to understand the technical nature of the project to avoid technical problems during the implementation process, causing higher costs and longer time of implementation.

It is necessary to develop standards for urban railways to apply for current and also future projects.

In addition, what needs to be done right now is to build a team of technical staff with expertise and knowledge in urban railway management.

Vu Diep

MORE NEWS

Credit package for social housing not as productive as hoped

Few have benefited from the VND15 trillion credit package for social housing as there is a limited supply of low-cost homes.

VIETNAM BUSINESS NEWS AUGUST 17

More effective tax collection of e-commerce necessary

VIETNAM NEWS HEADLINES AUGUST 17

Cultural industry to contribute 10% of Hanoi’s GRDP by 2045

Authority warns of scam South Korea labour export programmes

The Department of Overseas Labour under the Ministry of Labour, Invalids and Social Affairs have warned about scams targeting people who want to work in technical occupations in South Korea.

Textile firms call for favourable policies amid pessimistic prospects

With a pessimistic outlook for the second half of 2022, textile firms are calling for favourable governmental policies to turn their situation around.

Enterprises ignoring waste management to face penalty

Enterprises that are required to manage their waste and have yet to fulfill their payment obligations will be inspected, with a possible fine of up to VND2 billion for violations.

Favorable conditions pledged for Qatar’s funds, enterprises

Competent Vietnamese agencies are willing to create favorable conditions for Qatar’s investment funds and enterprises to seek investment opportunities in the country.

Woman posing for Tiktok video at Phu Quoc airport banned from flying for six months

The head of the Civil Aviation Authority of Vietnam Dinh Viet Thang has decided to issue a flight ban on a woman posing for a TikTok video at the Phu Quoc Airport tarmac for six months.

“1,000 public employees quitting jobs each month is inaccurate data”: HCM City

The Ho Chi Minh City Department of Home Affairs says the information that 6,177 public employees quit their jobs in the first half of 2022 is incorrect. These are actually statistics from January 1, 2020 to June 30, 2022.

Gov't sets up six working groups to inspect disbursement of public investment capital

Prime Minister Pham Minh Chinh has tasked six working groups to inspect disbursement of public investment capital in 41 ministries, state agencies and 18 localities where disbursement is below the national average rate of 34.47 percent as of July 31.

Vietnam to mobilise $360 billion for sustainable development targets

Vietnam needs to mobilise $360 billion for implementing its green and sustainable development targets by 2030.

Vietnam to make Apple Watch, MacBook for first time

Apple is in talks to make Apple Watches and MacBooks in Vietnam for the first time as the US tech giant looks to diversify production away from China, Nikkei Asia reported.

Japanese firm buys 35.1% stake at Vietnam’s power company

JERA Inc., a power generation company of Japan, has signed a deal to buy a 35.1% stake at Vietnam’s Gia Lai Electricity JSC (GEC) to tap the Southeast Asian nation's growing demand for electricity and further its own decarbonisation efforts.

Goalkeeper Dang Van Lam officially signs contract with Binh Dinh

Goalkeeper Dang Van Lam has signed a three-year contract with Binh Dinh FC and is expected to play his first match for his new team in the V.League 1 this weekend.

Vietnam faces shortage of Protamine sulfate

The Drug Administration of Vietnam (DAV) has sent a letter to provincial and municipal departments of health, hospitals and drug importers, asking them to supply information on stocks of Protamine sulfate.
back_to_top