North-South Highway: slow site clearance and material shortage

Some provinces have failed to meet the Prime Minister’s deadline for site clearance for the eastern part of the North – South Highway.

 

Cao tốc Bắc - Nam chậm mặt bằng, lo thiếu vật liệu

Some provinces have failed to meet the Prime Minister’s deadline for site clearance for the eastern part of the North – South Highway.

 

Six out of 11 sections of the eastern part of North-South Highway for the period of 2017-2020, which were converted to public investment, have started. Two other sections that are also invested by the State are expected to start in May.

According to the Ministry of Transport, site clearance has been far from expectations. The Prime Minister requested that it be generally accomplished in 2020. Nevertheless, by mid-Feb 2021, all 11 sections were struggling with site clearance. As many as 624 out of 652 kilometers of the Highway, 95.6%, have been handed over. The site handover in Ninh Binh, Thanh Hoa, Nghe An, Khanh Hoa provinces is much lower, 79.2%, 94.9%, 92%, and 91.5% respectively.

Around 80% of 11 resettlement areas are complete. Technical infrastructure has been slowly carried out. Only 30 – 38% of power, water, and telecommunication networks have been relocated.

The Transport Ministry planned to discuss directly with each province solutions for the required completion of site clearance.

Only 55.64 out of 63.37 kilometers of the Mai Son – NH45 expressway have been cleared and handed over to contractors. The section runs through three districts of Ninh Binh and eight of Thanh Hoa province. More than 8 out of 14.41km in Ninh Binh were handed over. The figure in Thanh Hoa was 47.46 out of 48.96km.

The main cause for delayed clearance in Ninh Binh is that Tam Diep district has failed to finalize the compensation price for different land types, identify persons qualified for job adjustment incentive scheme, and allocate resettlement area to a number of households.

Thanh Hoa has been facing difficulties in site clearance. It has the longest section of the Eastern part of North-South Highway, including Mai Son – NH45, NH45-Nghi Son, and Nghi Son – Dien Chau.

Mr. Nguyen Duc Trung, Deputy Director of Thanh Hoa Transport Department, said that the province has cleared 97% of the site. The slow progress was mainly due to some households’ requirements and demands beyond compensation regulations.

Inspecting the Mai Son – NH45 site with the Transport Minister Nguyen Van The on February 22, Mr. Mai Xuan Liem, Thanh Hoa Vice Chairman, said it would hand over the remaining site to contractors before March 15.

Cao tốc Bắc - Nam chậm mặt bằng, lo thiếu vật liệu

The Cao Bo - Mai Son section of the North - South Highway is expected to complete in 2021

 

Hard to find material sources

Apart from the slow site clearance, most contractors have faced a shortage of formation level materials (mainly soil).

Specifically, there is a lack of 1.6 million m3 of soil for Cam Lo – La Son section which passes through Quang Tri and Hue. Though there are 17 soil mines for Vinh Hao – Phan Thiet section, the supply is far below demand. The material shortage is also a problem for other sections namely Mai Son – NH45 and Phan Thiet – Dau Giay.

An additional 7 million m3 of soil and 400,000 m3 of crushed stone are needed for Nghi Son – Dien Chau section which is scheduled to launch in May.

According to some contractors, high demand for materials for the North – South Highway and section construction is being carried out simultaneously, which has led to mine owners’ increasing material prices, deepening difficulties for contractors.

Furthermore, provincial leaders have to review soil and stone mines for their approval, licensing and adjustment process. This takes a long time, affecting highway progress and quality.

Speaking about soil mine issues in his trip to inspect Mai Son – NH45 site on 22nd February, Minister Nguyen Van The demanded that provincial leaders review project and design documents to avoid the highway construction setbacks.

Vu Diep

'Special doctors' save lives on National Highway 5

'Special doctors' save lives on National Highway 5

Holding an emergency medical kit, Nguyen Ngoc Tuy rushes to help traffic accident victims after receiving a report of an accident from local residents.

 

MORE NEWS

Challenges for supermarket chains

The recent shutdown of multiple Bach Hoa Xanh (BHX) stores has been the talk of the town for the past few weeks. What prompted the leadership of this grocery store chain to come to such a decision despite the considerable growth in total revenue?

Re cakes: Phan Thiet’s specialty sweet treat

Re cake, a specialty of Phan Thiet City, Binh Thuan Province, tastes so delicious that no visitor can resist it.

A new move for open market operations

The State Bank of Vietnam (SBV) has recently made a new move regarding open market operations (OMO). Valuable papers are purchased at a competitive interest rate, instead of a fixed rate as before.

An insight into Vietnam’s indebtedness

National debt, or foreign debt, when reaching an excessive level, often leads to an economic crisis.

Nguyen eyes bigger competition after ASEAN Para Games wins

Tran Van Nguyen stands only 1.27m and has short arms and legs. But he has dominated the top podiums of many competitions.

Vietnam to have national marine spatial plan by 2030

A national marine spatial master plan is being developed, aiming to fuel the sustainable development of marine economic clusters and establish sea-based economic hubs by 2030.

Digital business lines developing well

Major tech companies are looking to expand in Vietnam, on the back of strong hardware export and IT figures for the country's telecom industry so far this year.

Vietnam targets launch of modern digital finance platform by 2025

Minister of Finance Ho Duc Phoc has signed a decision promulgating the Ministry of Finance's digital transformation plan to 2025, with vision to 2030.

Vietnam, Southeast Asia find ways to rise amid difficulties

Vietnam and the Southeast Asian region have managed to maintain economic stability and growth despite COVID-19 and the Russia-Ukraine conflict, according to experts.

CPI method of calculation is correct: economist

“Someone told me they had a feeling that the CPI is not correct. I asked them on what grounds. Scientifically, that cannot be proven,” said economist Vo Tri Thanh.

Real estate market is gaining balance: ministry

The real estate market of Vietnam showed signs of recovery and more balanced development in the second quarter of this year with increases in the number of successful transactions of apartments, houses and land.

What’s the future for the southeastern region?

Tran Dinh Thien, a respected economist, believes that if Vietnam can exploit its potential, it will be a big player in the world’s energy map in the future.

Experts warn of hot growth, oversupply of resort real estate

The massive development of resort real estate has led to an oversupply in the market.

Resorts infringing Phu Quoc Marine Protected Area forced to dismantle

Owners of dozens of illegal constructions of resorts and bungalows infringing Phu Quoc Marine Protected Area in Phu Quoc island in the Mekong Delta Province of Kien Giang will be forced to dismantle.

U.S. recommends adding birthplace info to Vietnam’s new passport

The U.S. is still reviewing Vietnam’s new passport and has asked visa applicants to submit their birthplace information.
back_to_top