Railway delayed by two decades traps Quang Ninh residents in deterioating homes

The 131-km-long railway project was approved in 2004, and construction started the following year. However, the project's completion has been delayed several times.

The construction of a 131-km-long railway connecting Hanoi and the coastal province of Quang Ninh has been delayed for nearly 20 years, trapping people living in the area set for construction as they have not been given the proper compensation. 

The construction of the 131-km-long railway connecting Hanoi and the coastal province of Quang Ninh has been delayed for nearly 20 years. VNA/VNS Photo Thanh Van

The 131-km-long railway project was approved in 2004, and construction started the following year. However, the project's completion has been delayed several times. 

In 2011, the construction was suspended as the project was among non-urgent public investment projects that the Government gave low priority for investment in the Government's Resolution No. 11/2011/NQ-CP.

To make room for the railway project, more than 3,600 families in Ha Long, Uong Bi, Dong Trieu, and Quang Yen have to relocate. However, nearly two decades later, they have still not received proper compensation to allow them to do so. 

In addition, they are not allowed to make any transactions relating to the houses in the project areas or even repair the houses, even though they are degraded. 

Tran Van Nhuan, a resident of Quang Trung ward, Uong Bi City, said that for years he wanted to transfer the land use rights or build a new house for his children as they all grew up, got married and had children.

"As my house is in the railway project area, I can do nothing with it," Nhuan said, adding that his children and his grandchildren were now all living together in an old cramped house over 50 years old.

A degraded house located in the railway project area, whose owners are not allowed to repair it. VNA/VNS Photo Thanh Van

Nhuan's daughter-in-law Du Thi Hop said that whenever it rained, rainwater leaked everywhere in the house.

Another resident, Vu Van Mien in Mao Khe Ward, Dong Trieu Town, is the breadwinner of his family of three, with his ill son and a young grandchild.

His house is small and has degraded over the years, but he cannot repair or sell it as it is in the project area. 

Mien said he wished authorities at both central and local levels quickly make a plan to remove and shorten the project's implementation time.

"If it continues for a few more years, people who are over 70 years old like me can't wait," Mien said.

As the project is suspended, affected families have not received compensation and have no money to buy land elsewhere.

As the project is unfinished, compensation for site clearances has also stopped. Out of more than 3,600 affected households, around 1,600 have been approved for compensation, support, resettlement and payment plans. More than 500 of those approved are still waiting for payment. 

More than 1,200 households are still waiting to receive initial approval. 

Le Van Luong, director of the Centre for Land Fund Development in Dong Trieu, said that the town has 1,372 households affected by the project. Of them, only 902 were approved for compensation.

"The prolonged project has greatly affected people's lives and political security situation," he said.

Over 400 households have not yet been approved for land clearance compensation but cannot convert the land use purpose, change the land use right or repair/build. Those affected had to petition repeatedly for years.

According to Truong Quoc Huy, Vice Chairman of the People's Committee of Quang Trung Ward, Uong Bi City, households had to move their houses to make room for the construction of the railway line and additional areas for the railway safety corridor. According to the Construction Law, people are not allowed to build new works within the safety corridor of technical infrastructure works.

"The problem is that households will not be compensated for the areas that serve railway safety corridors," he said.

"There are many households that have had almost all of their existing land acquired to serve the project, but have not been compensated, so they do not have the financial resources to buy land elsewhere and have to continue to live in degraded houses," Huy said. 

Transport Ministry proposes to continue railway project

According to the Ministry of Transport, the national railway network plan for the period 2021-2030 continues to determine the completion of the Yen Vien-Pha Lai-Ha Long-Cai Lan railway. The project aims to harmoniously develop modes of transport, ensure connectivity with optimised costs and improve the region's socio-economic development and localities along the route.

The railway is designed with a speed limit of 120 km/h for passenger trains and 80 km/h for freight trains. Once completed, the new line would cut the journey from Ha Long to Yen Vien to just an hour and a half to two hours for passenger trains and three to four hours for freight trains.

The railway project has a length of 131 km, including 43 km of new construction and 88 km of renovation and upgrades. It has a total investment of VND7.665 trillion, divided into four sub-projects operating independently. The project began in 2005. However, as the project was one of those suspended to cut public investment under the Government's Resolution No. 11/2011/NQ-CP, work was suspended in 2011.

Only one of four sub-projects, the Ha Long-Cai Lan section, was completed and put into operation.

The remaining three sub-projects, Yen Vien-Lim, Lim–Pha Lai, and Pha Lai–Ha Long, have implemented compensation, site clearance, and road construction.

Source: Vietnam News

MORE NEWS

Free piano class for the elderly in HCM City

A piano class has been run free-of-charge for elderly people in Ho Chi Minh City for the past five years.

President wraps up State visit to RoK

President Nguyen Xuan Phuc and a high-ranking delegation of Vietnam arrived in Hanoi on December 7 morning, concluding a successful State visit to the Republic of Korea (RoK) at the invitation of President Yoon Suk-yeol.

Business safety in the digital age

Vietnamese businesses are facing challenges related to cyber security and difficulties adapting to digital transformation.

Tax refunds worth trillions of VND

Tax bodies are working on problems related to VAT refunds in order to help businesses get money to invest in operations, following a dialogue held last week.

Legal loopholes exist for trading forbidden goods

Many students believe that e-cigarettes are not toxic, but are fragrant and stylish.

Quang Ninh to develop night-time economy, awaken tourism

On July 27, 2010, the Prime Minister signed a decision approving Vietnam’s night-time economy development plan.

National Geographic Traveler explores Hanoi

Atmospheric night markets, historic temples, sleek cocktail bars, and an evolving culinary scene of Hanoi have conquered the heart of a journalist from the world-class travel magazine.

VN considering feasibility of North-South high-speed rail project

Minister of Transport Nguyen Van Thang proposed that World Bank (WB) help Vietnam find suitable partners for the country’s North-South high-speed rail project.

Apple adds Hoang Sa, Truong Sa islands to its map at the request of Vietnam

At the request of the Ministry of Information and Communications, Apple has corrected the mistake, adding Hoang Sa (Paracel) and Truong Sa (Spratly) Archipelagos to the map on the Apple Maps application.

Tax revenue from e-businesses below expectations

Tax revenues from e-commerce activities have risen over the years, but they are still far behind the industry’s expansion rate, the Ministry of Finance reported.

Vietnam hosts over 100 million domestic visitors, surpassing all forecasts

Domestic tourism is strongly bouncing back, recording more than 100 million visitors so far this year, higher than all forecasts and up 1.5 times compared to the yearly target of 60 million.

Voting begins for top 10 culture, sporting, and tourism events in 2022

Repatriating the Nguyen Dynasty’s imperial seal, the nation’s hosting SEA Games 31, and the reopening of international tourism as of March 15 are among the nominations for voting in the top 10 culture, sporting, and tourism events of the year.

National forum on development of digital enterprises due on Dec. 8

A national forum aimed at fostering greater development among local digital enterprises is scheduled to get underway on December 8 at the National Convention Centre in Hanoi.

Quang Ninh has new acting chairman

Standing Deputy Prime Minister Pham Binh Minh has signed a Decision No 1509/QĐ-TTg on December 2th 2022 to assign the acting chairman of People’s Committee of Quang Ninh to Cao Tuong Huy.

Vietnam to develop strategic infrastructure to lure more RoK investment: President

Vietnam will strongly develop its strategic infrastructure system to lure more investment from the Republic of Korea (RoK), President Nguyen Xuan Phuc told more than 500 enterprises attending the Vietnam-RoK Business Forum in Seoul on December 6.
back_to_top