The financial issues clouding ambitious North-South railway

The North-South high-speed railway line is a large-scale project with a total investment of around $58.7 billion which could facilitate not only cargo transport at an operational speed of up to 200km/h but also reduce travel time

between Hanoi and Ho Chi Minh City to around eight hours. However, 2018’s pre-feasibility study by the consortium of consultants has shown that several financial problems need to be considered for the project to be successful.

{keywords}
By Dr. Vu Dinh Anh - Expert, Price Market Research Institute, Ministry of Finance.

The ninth chapter of the study states relevant legal documents for the project financial calculations. However, because the study was made two years ago, some of the referred documents are already outdated, for instance, when it comes to calculations of labour costs.

The same chapter mentions costs for infrastructure, equipment, land clearance, taxes, and more. Accordingly, the total investment required for the first phase of the project, Hanoi-Vinh-Nha Trang-Ho Chi Minh City, amounts to $24.7 billion, while the second phase for Vinh-Nha Trang would cost around $34 billion. Both sections bring the total required investment to $58.7 billion, equalling a near 25 per cent of 2018’s GDP. However, the calculations for these numbers are equally outdated and contain many variables that have already changed.

Besides this, the total interest expense and commitment fees were set at $258 million and are based on the assumption that interest rates during construction would be at 0.2 per cent per year. However, Vietnam has become a low-middle-income country since 2011 and is expected to become a high-middle-income country by 2030, meaning that concessional loan conditions will have major changes that need to be included in the calculations.

The current total investment is high, even higher than originally pre-calculated in 2010, and double that of the Ministry of Planning and Investment’s announcement at the beginning of the year. Therefore, it is necessary to explain the reasons for the differences to the previous estimates.

In addition, the pre-feasibility study outlines and analyses three plans to mobilise the nearly $60 billion for the project. One option includes the entire state budget, the second the entirety of official development assistance (ODA), and the third a combination of state and private capital in public-private partnerships with various overseas markets. However, the evaluation of all three options is not convincing as they are all based on previous GDP forecasts, which is not reasonable or practical.

Meanwhile, forecasts from the World Economic Forum, the World Bank, and the Prime Minister’s Advisory Group from 2018 are now very inaccurate and far from reality. Vietnam’s growth rates since were higher than forecast, however, due to the pandemic’s impact, this year’s growth rate stands at around 2-3 per cent, which renders prospects for the period until 2025 still uncertain.

The study stated that it is possible to mobilise 0.69 and 0.53 per cent of GDP for the project’s two phases, respectively, even up to 1.67 and 1.29 per cent at the highest. However, the study does not base these estimates on the actual investment developments in the previous period, the capital demand for projects, and the change in capital management according to the medium-term public investment plan.

In particular, the three capital mobilisation options stated in the report are not feasible, and state budget expenditure has been and remains at a very high level. To balance the state budget and reduce its deficit and public debt, instead of continuing to increase the state’s revenue, it can only reduce its expenditures, especially investment and development costs in infrastructure construction.

Vietnam set the target to reduce the state’s budget deficit to below 3 per cent of GDP by 2030. However, the budget deficit is causing difficulties in spending capital for the North-South high-speed railway as well as for borrowing additional funds, while ODA is forecast to be very limited in the coming years. The state budget deficit between 2006 and 2019 increased sharply in both absolute numbers and as a percentage of GDP compared to the previous period. The current global economic crisis promises to make the state budget deficit even worse.

Finally, the rise in public and external debts makes the state borrow even more. According to the Ministry of Finance, public debt has been growing rapidly from 56.3 per cent of GDP in 2010 to a peak of 63.7 per cent in 2016, only slowly decreasing in the following years until 2019 to around 56 per cent of GDP.

Foreign debt consists mainly of concessional loans, with the average loan term being 20 years at an interest rate of about 1.6 per cent per year, but because domestic debt comes mainly through short-term government bonds with high interest rates, pressure and direct debt repayments increase rapidly in the short term.

Currently, Vietnam is categorised as a low-middle-income country, so ODA mobilisation tends to decrease gradually with shorter terms and increased interest rates which lead to public debt obligations while state debts tend to increase.

To sum up, although it has been meticulously prepared, the financial problems of the North-South high-speed railway remain, and forecasts and planning need to be brought closer to reality with updated direction and variables in accordance with forecasts in each financial plan.

In addition, each financial option should be built based on updating and analysing the situation as well as economic growth trends, state and development expenditures, and the ability to utilise public debt and ODA loans to increase the feasibility of each possible direction.

 

The pre-feasibility study by the consortium of consultants for the North-South high-speed railway project proposed to build a railway line of about 1,560km, running along the North-South corridor of the country and passing through 20 localities while connecting Hanoi and Ho Chi Minh City. The proposed trains are designed for a speed of up 350km/h, and the commercial operating speed for passenger transport was planned to be 320km/h.

The planned investment capital amounts to $58.7 billion, separated into two project phases. Phase 1 from 2020 to 2032 is meant to research and invest in the construction of the Hanoi-Vinh-Nha Trang-Ho Chi Minh City sections. In the second phase from 2032 to 2050, the construction of Vinh-Nha Trang would take place, in which the Vinh-Danang and Danang-Nha Trang sections were set to be completed in 2040 and 2050 respectively. VIR

 

North-south trains to be halted due to Covid-19

North-south trains to be halted due to Covid-19

As new local infections of Covid-19 are rising, Vietnam Railways Corporation has announced the suspension of SE11 and SE12 trains on the Hanoi-HCMC route from August 1.

Nearly US$84 million invested in upgrading north-south railway

Nearly US$84 million invested in upgrading north-south railway

The Ministry of Transport has approved a 1.95 trillion VND (83.85 million USD) project on upgrading weak bridges along the railway connecting Hanoi to Ho Chi Minh City.  

MORE NEWS

Vietnamese movie honoured at France festival

“Tro tan ruc ro” (Glorious Ashes) by Bui Thac Chuyen won the "Golden balloon" award (Montgolfière d'or) at the Festival des 3 Continents 2022 which took place in Nantes, France, from November 18 – 27.

VIETNAM BUSINESS NEWS NOVEMBER 28

Gloomy outlook for exporters of aquatic products next year

Male model finishes fourth runner-up at Mister Grand International

Nguyen Vu Linh, Vietnamese representative at Mister Grand International 2022, was awarded the fourth runner-up title during the male pageant’s grand final held in Trinidad and Tobago on November 26.

Magnitude three earthquake hits northern border locality

An earthquake measuring three on the Richter scale jolted Ha Giang city in the northern border mountainous province of the same name on November 28.

Foreign fans congregate at Hanoi beer hub for 2022 World Cup

German and Spanish fans make their presence felt on backpackers street Ta Hien in Hanoi’s Old Quarter on November 28, supporting their respective countries at the ongoing 2022 FIFA World Cup underway in Qatar.

AI - the future of retail

Technology is changing the retail sector, with artificial intelligence (AI) shaping shopping centers and stores of the future.

Hanoi to celebrate New Year with drone light show and marathon

A countdown event, concert, drone light show and an international marathon will be held in Hanoi to celebrate the New Year 2023.

How will Vietnam escape the 'middle-income trap'?

Vietnam aims to become a higher average income country and a high income country by 2035 and 2045. However, to reach that goal, it will have to overcome challenges, especially institutional ones.

HCM City develops food streets to attract tourists

Ho Chi Minh City is focusing on developing food streets to attract more tourists and make them spend more during their stay in the city.

Int’l experts, organisations believe in Vietnam's sustainable growth potential

Experts, and representatives of international organisations, and investment funds have shown their belief in the potential for sustainable growth in Vietnam in the coming tỉme.

Why has HCM City removed 'residential people’s groups'?

With the elimination of over 25,000 "residential people’s groups", HCM City has cut 38,000 part-time officers.

Duan wins Hanoi Midnight marathon title, eyes SEA Games slot

Almost 10,000 elite and amateur runners registered to participate in the event. The number was double that of the first edition in 2020.

HCM City seeks to prevent illegal waste dumping

HCM City’s environmental sector is taking steps to prevent illegal dumping of domestic waste transported from neighbouring provinces to the city.

Macroeconomic and monetary policies key to improving economy

A volatile global market, the COVID-19 pandemic, approaching the limit to horizontal expansion and inefficient macroeconomic policies in the past...

Domestic tourism increases but spending remains low

The domestic tourism market was a lifesaver during the difficulties of the COVID-19 pandemic, but local spending on tourism is still low and needs a boost, experts have warned.
back_to_top