On November 25, Permanent Deputy Prime Minister Pham Gia Tuc chaired a meeting with relevant ministries, local authorities and businesses to address obstacles and accelerate the construction of phase one of Long Thanh International Airport.
According to the Government Portal, ACV reported that the value of completed work under Component Project 3 had reached VND 76.95 trillion, equivalent to 88.63% of the contract value. Disbursement stood at VND 49.51 trillion, or 57% of the contract value.
However, due to a combination of objective and subjective factors, ACV concluded that the entire component project could not be completed in 2026 as stipulated in the contractual schedule.

Several major construction packages, including the passenger terminal, Cargo Terminal No. 1, parking facilities and airport management systems, are expected to be completed or finish testing in June 2027.
ACV identified several major obstacles affecting the implementation of Component Project 3. Resolving these issues is essential for final construction acceptance and obtaining the necessary licences to put the airport into operation.
The corporation proposed measures to address outstanding issues within the relevant authorities’ jurisdiction.
Based on the actual progress of Component Project 3 and facilities under Component Project 4, ACV requested that the Government assign the Ministry of Construction to conduct a comprehensive review of all component projects and submit a proposal to competent authorities to extend the implementation deadline for phase one to 2027-2028.
Concluding the meeting, Permanent Deputy Prime Minister Pham Gia Tuc called for urgent action to resolve outstanding problems, stressing that existing violations must not be legitimised and new violations must be prevented.
Project investors, ministries, agencies and local authorities must proactively resolve matters within their jurisdiction and refer issues beyond their authority to competent bodies for consideration and decision.
The deputy prime minister instructed ACV to assume full responsibility before the Government and the Prime Minister for the progress and quality of Component Project 3 and its construction packages, in its capacity as the project investor and airport operator.
ACV must also review and resolve payment-related obstacles in accordance with applicable regulations, ensuring sufficient financial resources for contractors to continue construction.
For materials and equipment subject to outstanding issues, ACV must take responsibility for assessing their quality, suitability and compliance with project requirements.
Regarding ACV’s proposal to establish an equipment quality assessment council, the deputy prime minister stressed that the corporation must retain the leading role and assume responsibility for its assessments.
The project investor may invite specialists from ministries, universities and research institutes to provide technical expertise.
Investigation into Long Thanh airport violations to be accelerated

The Ministry of Construction will remain the lead agency responsible for monitoring, inspecting and accelerating project implementation, while providing ACV with guidance on investment project management and construction quality control.
The ministry must also review ACV’s proposals, instruct the corporation to complete relevant documentation, identify specific outstanding issues and develop solutions supported by clear legal grounds.
The Ministry of Finance will coordinate with relevant agencies to help ACV resolve obstacles involving payments, financial mechanisms, price appraisals and exchange rates applied to imported equipment.
Meanwhile, the Ministry of Public Security has been instructed to accelerate investigations and address violations in accordance with the law, clearly identifying the individuals involved, their actions and respective responsibilities.
The ministry must also share relevant information with ACV and the Ministry of Construction to enable competent authorities to address outstanding project issues.
Regarding the construction schedule, the deputy prime minister instructed ACV to review all remaining work under Component Project 3 and establish clear milestones for construction completion, equipment installation, testing, trial operations and the commencement of airport operations.
Given that the project cannot be completed in 2026 as envisaged under the investment policy approved by the National Assembly, ACV must submit a report to the Government and the Ministry of Construction within one week of the meeting.
The Ministry of Construction must report to the Government on project progress before December 10, 2026, for submission to competent authorities for consideration and a decision on adjusting the investment policy.
ACV must require contractors to mobilise maximum available personnel, machinery, equipment and financial resources, increase working shifts, and accelerate construction and disbursement.

Contractors failing to fulfil their contractual obligations must face appropriate action by ACV or competent authorities.
The deputy prime minister emphasised that passenger safety and convenience are among the most important criteria for an international airport.
ACV must ensure coordinated implementation across all construction packages while fully complying with technical standards, administrative procedures and environmental protection regulations.
Construction deadlines must not be met at the expense of quality or safety.
Long Thanh International Airport is one of Vietnam’s most significant infrastructure projects and is expected to become a major regional aviation hub.
With an ultimate design capacity of 100 million passengers annually and a total investment exceeding USD 16 billion, the airport is expected to become a new symbol of Vietnam’s aviation industry.