Built with public funds between 2010 and 2020 to tackle rural household waste, numerous incinerators and treatment facilities in Thanh Hoa, Nghe An and Ha Tinh now stand idle, wasting public investment.
Urbanization and economic development have made waste management an increasingly urgent issue across Vietnam's north-central provinces. As waste volumes increase, shortcomings in local treatment infrastructure and capacity have become increasingly apparent.
New regulations imposing stricter emission control requirements are placing additional pressure on local waste treatment systems.
Against this backdrop, what solutions can address infrastructure limitations, improve waste management efficiency and ensure sustainable development?
The series "Waste management in north-central Vietnam: The challenges of outdated infrastructure" examines the current situation, identifies investment and operational bottlenecks, and explores solutions to improve waste treatment capacity across the region.
A $1.7 million project still in trial operation after four years
The first phase of a solid waste treatment project in the former Quy Hop District, Nghe An Province, had a total investment of VND44 billion ($1.7 million).
Approved in 2010, the project did not begin construction until 2019. Its first phase was completed in October 2021, comprising an access road, an operations building, a waste incinerator and a landfill cell.
The facility was handed over in early 2022 but has yet to begin official operations due to unresolved administrative procedures concerning its management and operation.
The first phase of the solid waste treatment project in the former Quy Hop District, Nghe An Province. Photo: Tran Tuyen
Large volumes of waste have filled the landfill cell despite the facility only being in trial operation. Photo: Tran Tuyen
In September 2022, the People's Committee of the former Quy Hop District called for investors before signing a contract assigning Song Lam Environment and Urban Services Joint Stock Company to conduct trial operations at the facility.
During this period, an old landfill located approximately five kilometers away continued receiving household waste. Covering more than one hectare, the landfill was situated within a residential area.
By the end of 2023, it was forced to close due to overloading.
Speaking about the VND44 billion project, Pham Cong Truyen, head of the Economic Division of Quy Hop Commune, said the facility was intended to serve communes established within the former Quy Hop District.
"Due to the large volume of waste generated, the landfill cell has already reached full capacity despite only being in trial operation. It can no longer receive additional waste," Truyen said.
As the facility serves multiple communes, the Quy Hop Commune People's Committee has asked provincial authorities to consider investing in the project's second phase and completing the remaining infrastructure in accordance with the approved plans.
In Ha Tinh Province, the household waste treatment facility serving the former Vu Quang District, now located in Thuong Duc Commune, also stands idle.
Approved by the provincial People's Committee in 2020, the project had a total investment of nearly VND15 billion ($577,000), with the People's Committee of the former Duc Huong Commune acting as the project owner.
The facility was designed to cover 3.4 hectares, with an incineration capacity of approximately 10 tons of waste per day.
Hundreds of tons of waste have accumulated at the inactive Thuong Duc waste treatment plant. Photo: Sy Thong
Machinery and equipment at the facility are deteriorating. Photo: Sy Thong
Construction began in late December 2020, with operations initially scheduled to commence in May 2021.
However, construction delays meant the facility did not become operational until late 2023.
After a relatively short period of operation, the plant was forced to suspend activities in September 2025 due to a malfunction in its incinerator.
During a visit by VietNamNet reporters, machinery and equipment inside the facility were covered in dust, several roofing panels were damaged, and steel structures showed signs of corrosion.
Nguyen Thanh Son, chairman of the Thuong Duc Commune People's Committee, confirmed that the plant had temporarily suspended operations due to technical problems.
"Local authorities are reporting the situation and seeking provincial approval for an appropriate solution," Son said.
According to Son, the facility remains under warranty. Local authorities have requested that the construction and installation contractor carry out repairs, but the work has yet to be completed.
Waste incinerators that failed prematurely
In Dai Loc Commune, Thanh Hoa Province, a waste incinerator was developed with nearly VND7 billion ($269,000) in public funding.
Covering approximately 1.5 hectares, the facility began operations in 2015 with a designed capacity of 500 kilograms per hour, equivalent to 12 tons per day.
However, its actual treatment capacity fell short of initial projections.
The waste incinerator in Dai Loc Commune has been abandoned for years. Photo: Le Duong
Inside the abandoned waste treatment facility. Photo: Le Duong
After approximately five years of operation, the incinerator shut down and has remained idle ever since.
At the site, steel structures have become rusty, corrugated metal roofing has deteriorated, and weeds have overgrown the premises.
A similar situation has unfolded in Hoa Loc Commune, Thanh Hoa Province, where a waste incinerator was constructed in 2018 with an investment of approximately VND5 billion ($192,000) and a designed treatment capacity exceeding seven tons per day.
However, from the early stages of operation, daily waste volumes occasionally exceeded 10 tons.
The system also experienced frequent technical problems, while repair costs exceeded the local authority's financial capacity.
In July 2022, the incinerator officially ceased operations.
Similar problems have been observed at the waste incinerator in Xuan Binh Commune, Thanh Hoa Province.
The Phuong Thanh waste treatment plant has been closed for years. Photo: Sy Thong
Developed with an investment exceeding VND11 billion ($423,000), the facility was completed in late 2019 but operated for only a short period before shutting down. Several infrastructure components have since deteriorated.
In Ha Tinh Province, the waste incinerator at the Phuong Thanh landfill in the former Duc Tho District was developed with an investment exceeding VND6 billion ($231,000).
Construction began in July 2016, and trial operations commenced in early 2018, with a designed capacity of approximately 24 tons per day.
However, its actual treatment capacity was insufficient to handle the volume of waste generated.
The incinerator ceased operations and has remained abandoned for years.
Meanwhile, waste continued to be transported to the landfill, accumulating in large piles estimated at approximately 2,000 tons, according to figures previously released by local authorities.
A representative of the Duc Tho Commune People's Committee said the plant had been closed for a long time.
One of the identified problems was that the facility's location failed to meet regulatory requirements regarding minimum distances from residential areas.
Numerous waste treatment facilities have ceased operations
Nguyen Thi Minh Hue, head of the Environmental Division of the Thanh Hoa Department of Agriculture and Environment, said the province had invested in 23 waste treatment facilities equipped with 24 conventional incinerators, with an average treatment capacity of 10-20 tons per day.
Currently, only eight incinerators remain operational, while 16 have ceased operations.
Sixteen waste incinerators across Thanh Hoa Province have ceased operations. Photo: Le Duong
Among the remaining operational incinerators, several facilities have adopted microbial composting combined with waste sorting before incineration, initially delivering positive results.
For five of the suspended facilities, commune-level authorities have proposed renovation, upgrades or attracting investment in alternative treatment technologies to avoid wasting public funds.
According to Hue, the problems stem not only from management and operational difficulties, insufficient maintenance funding and opposition from residents concerned about pollution, but also from outdated technology.
Many incinerators were installed years ago and have limited treatment capacity, making them unable to cope with increasing waste volumes or comply with current environmental standards.
Numerous incinerators have deteriorated or suffered equipment failures. Some cannot effectively process waste with high moisture content, while others require costly repairs.
Consequently, local authorities have been forced to suspend operations and redirect waste to centralized treatment facilities.
Overloading has also affected larger waste treatment facilities originally developed at the district level.
Thanh Hoa currently has 21 centralized landfills funded by provincial and district budgets, covering a combined area of nearly 60 hectares and containing approximately four million tons of accumulated waste.
Four facilities have stopped receiving waste, while 17 remain operational.
Among the 17 operational facilities, three have adopted treatment technologies that eliminate direct landfilling, eight have yet to reach full capacity, and six are already overloaded.
Despite exceeding their capacity, overloaded facilities continue receiving waste daily because advanced treatment facilities across the province cannot handle the volume of waste generated.
An official from the Nghe An Department of Agriculture and Environment said the incineration technology selected for a waste treatment project had been considered advanced when the project was initially approved.
However, after years of inactivity, the originally designed processing system no longer complies with current environmental standards.
"If the project proceeds, the investor will have to review and upgrade its technology. Current standards require not only stricter emission controls but also increasingly emphasize waste treatment combined with energy recovery," the official said.