Will the State buy back four BOT toll stations?

A government report shows that problems still exist at four BOT (build, operate, transfer) toll stations. Because of their special properties, it has been difficult to maintain their operations.

The government’s report to the National Assembly on October 5 updated the issues with problematic BOT toll stations that the public has complained about.

Will the State buy back four BOT toll stations?

To date, the problems at 15 out of 19 toll stations have been settled, and traffic safety and public order have been stabilized. Meanwhile, the problems of the other four stations have not been settled because of special conditions.

Bim Son Station which collects fee for the bypass in the western part of Thanh Hoa City, is one of them. The station is located outside the project. If fees continue to be collected, this may cause risks in public order and traffic safety.

Implementing the government’s conclusions released on June 26, 2019, the Directorate for Roads joined forces with authorities of Thanh Hoa province and investors to consider a plan to relocate the station to the western bypass.

However, since there are three parallel lines (Highway 1 which goes through Thanh Hoa City, eastern bypass and western bypass) and there are many intersections on the route, vehicles can avoid the station. Therefore, the existence of a toll station on the western bypass won’t help to collect fees to recover the investment capital for the BOT project.

The solution under consideration now is using the state’s money to pay the investors.

The toll station on Highway No 3 which collects fee for the BOT project on building Thai Nguyen – Cho Moi Road and upgrading the Highway No 3 (Km 75 – Km 100) is in the same situation.

A government report shows that problems still exist at four BOT (build, operate, transfer) toll stations. Because of their special properties, it has been difficult to maintain their operations.

The Ministry of Transport (MOT), after working sessions with the Thai Nguyen provincial authorities, have agreed on reducing the fee and made public the reductions.

However, according to the Thai Nguyen People’s Committee, many people have disagreed, gathering at the toll station and the province’s Citizen Reception, requesting to remove the station and asking for a dialogue with agencies.

As instructed by the Prime Minister, MOT and the provincial authorities worked on a solution to ensure the public order security and traffic safety before allowing the investors to collect fees at the Highway No 3 station in accordance with the fee reduction plan.

However, the local authorities warned that some problems in security may arise.

“If the situation becomes too complicated, the ministry will stop collecting fees and ask the Prime Minister to arrange state money to pay the investors and remove the toll collection on Highway 3,” the report said.

 

As for T2 Station, which collects fee for the BOT project on upgrading Highways 91 and 91B, the report said MOT and relevant agencies, after considering the public order and security, have agreed that it would be better not to continue to collect the fee at T2.

They will report to appropriate agencies and ask for allocation from the state budget to support the investments for Highway 91B, and assign the Can Tho City People’s Committee to take over, manage and maintain the highway.

Regarding the La Son – Tuy Loan Station, the Ministry of Finance has proposed not to use the station to collect fee to recover the investment capital of the project, but use the state budget.

The viewpoint of MOT and the Ministry of Justice is that the fee collection of La Son – Tuy Loan Station is not covered by the Law on Management and use of public property, so the fee collection should be allowed to continue.

Financial plans

The report also pointed out that difficulties in handling the problems at these stations have led to decreases in the projects’ revenue.

Experts have warned that if the problems cannot be solved, financial plans will be upset, and bad debts will increase, thus affecting the nation’s monetary management policy and the investment environment and putting pressure on the state budget.

Regarding the road service fee remissions, the government’s report pointed out that fee exemption and reductions have been proposed for 100 percent of the BOT projects put under the management of MOT.

Under the contracts signed with the investors, the prices will be adjusted once every three years and the fee will increase by 18 percent for every adjustment after getting approval from state agencies.

The fee increase is due for 49 projects. However, the government has instructed not to raise the fees now. So, many financial plans will be "broken" if the price adjustment is delayed to 2022. 

Vu Diep

Delayed BOT projects threaten to disrupt future power supply

Delayed BOT projects threaten to disrupt future power supply

A series of build-operate-transfer power projects are lagging behind set schedules by as much as a year due to the global pandemic, threading concern into the power supply issue in the coming time.

Nearly US$3 billion worth of loans to BOT projects likely to become bad debt

Nearly US$3 billion worth of loans to BOT projects likely to become bad debt

Forty-nine BOT (build-operate-transfer) transport projects have been reported as having revenue below expectations.

 
 

Other News

.
“Locking power in the cage of mechanisms” and 13th National Party Congress personnel work
“Locking power in the cage of mechanisms” and 13th National Party Congress personnel work
FEATUREicon  13/10/2020 

"Locking power in the cage of mechanisms" is an issue that has been repeated in many speeches by Party Secretary General and President Nguyen Phu Trong.

Long Thanh Airport project awaits disbursement of funds
Long Thanh Airport project awaits disbursement of funds
FEATUREicon  13/10/2020 

The government’s report to the National Assembly on the implementation of the Long Thanh International Airport project on October 9 shows that little has been done over the last five years.

Aspiration 2045
Aspiration 2045
FEATUREicon  12/10/2020 

For many years, the Vietnamese Government has always focused on setting the goal of annual GDP growth because high growth can help the country narrow the development gap with neighboring countries and the rest of the world.

Solar power: projects line up, policy under consideration
Solar power: projects line up, policy under consideration
FEATUREicon  12/10/2020 

Tens of solar power projects are awaiting to be added to the list of power generation projects to be developed. Meanwhile, ministries are still discussing the new pricing mechanism after the preferential FIT expires.

SOE equitization: state takes loss, and investors lose money
SOE equitization: state takes loss, and investors lose money
FEATUREicon  12/10/2020 

Many state-owned enterprises (SOEs) have been equitized but have not seen considerable changes as the state's ownership ratio remains high. Many of them are still taking losses and struggling to survive.

Constantly building the "the people’s heart posture", the people's security posture at sea
Constantly building the "the people’s heart posture", the people's security posture at sea
FEATUREicon  16/09/2020 

The Vietnam Coast Guard in recent years has played a great role in the task of ensuring national defense and security, making a solid foundation for people to do business and live.

Vietnam’s 2G decision paved way for digital growth
Vietnam’s 2G decision paved way for digital growth
FEATUREicon  12/10/2020 

In 1993, despite many dificulties, Vietnam decided to choose GSM (The Global System for Mobile Communication) technology for a mobile network. It was one of a few countries pioneering 2G.

Code of Conduct in the East Sea: a long and arduous road
Code of Conduct in the East Sea: a long and arduous road
MARITIME SOVEREIGNTYicon  08/10/2020 

During the ASEAN Regional Forum (ARF) on September 12, the ASEAN Foreign Ministers once again called for the early completion of the Code of Conduct in the East Sea (COC). But obstacles remain.

Additional economic relief packages in the pipeline
Additional economic relief packages in the pipeline
FEATUREicon  07/10/2020 

The Government is drafting second economic relief packages aimed at assisting the national economy, especially businesses, in the face of the ongoing COVID-19 crisis.

What are the key factors influencing travel decisions now?
What are the key factors influencing travel decisions now?
FEATUREicon  10/10/2020 

Safety of tours and people’s financial capability are the decisive factors affecting people’s travel plans from now to the end of the year, a survey has found. Travelers are choosing short tours and going in small groups.

Special moment for Vietnam: time to rise as opportunities open up
Special moment for Vietnam: time to rise as opportunities open up
FEATUREicon  11/10/2020 

As the global production network has been seriously disrupted, now is the time for Vietnam to reposition itself in the supply chain.

Silicon Valley in Southeast Asia: Da Nang lures Japanese technologies
Silicon Valley in Southeast Asia: Da Nang lures Japanese technologies
FEATUREicon  06/10/2020 

Da Nang has caught the attention of Japanese ICT firms thanks to its favorable investment environment.

Shifting from analog to digital: the power of innovative thinking in the postal services sector
Shifting from analog to digital: the power of innovative thinking in the postal services sector
FEATUREicon  10/10/2020 

More than 30 years ago, when the country fell into a crisis, it was the strong innovative mindset that brought the postal industry to succeed in establishing digital transformation.

Private sector – an important driving force of VN economy
Private sector – an important driving force of VN economy
FEATUREicon  04/10/2020 

The private economic sector's strong development to become an "important driving force" of the Vietnamese economy and other economic achievements have the contribution of the Central Economic Committee.

How to keep the sun always shining?
How to keep the sun always shining?
FEATUREicon  07/10/2020 

Vietnam is setting specific economic timelines and targets with a desire to become a high-income country - something not many countries can do. How should that aspiration be energized?

"Happiness" is a highlight in the 13th National Party Congress’s draft documents
"Happiness" is a highlight in the 13th National Party Congress’s draft documents
FEATUREicon  06/10/2020 

One of the new points of the 13th National Party Congress documents is to thoroughly grasp the spirit of innovation, arouse the values of Vietnamese people, and take advantage of the 4.0 technology revolution, for a "prosperous and happy Vietnam".

The nation's "career" of today
The nation's "career" of today
FEATUREicon  05/10/2020 

Preparing for the 13th Party Congress after 75 years of independence and 45 years of reunification, Vietnam has made many spectacular strides compared to the past.

The street that sells "magic medicine" in Saigon
The street that sells "magic medicine" in Saigon
FEATUREicon  03/10/2020 

Chau Van Liem Street in District 5 in Ho Chi Minh City has become a place where aphrodisiacs are sold illegally.

National brand: Intellectual property cannot be ignored
National brand: Intellectual property cannot be ignored
FEATUREicon  03/10/2020 

In any national branding strategy, we cannot ignore intellectual property (IP), an effective tool to maintain a positive national image.

Incurring big losses, Vietnam railway faces serious challenges
Incurring big losses, Vietnam railway faces serious challenges
FEATUREicon  06/10/2020 

The number of train trips Vietnam Railways (VNR) provided in February-May 2020 decreased by 2,886 compared with the same period last year, mostly because of Covid-19. The occupancy rate in H1 was only 56 percent.

 
 
 
Leave your comment on an article

OR QUICK LOGIN