Hanoi urban metro line’s elevated section commissioned (Photo: VNA) |
The train departed from the Nhon depot to the S8 station, then it ran in reverse.
As scheduled, the interlocking commission will be carried out by foreign experts of the contractor in compliance with the project's technical requirements and procedures.
According to the Metropolitan Railway Management Board (MRB), six out of 10 trains were transported to the Nhon depot for pairing, calibrating and performing static and dynamic tests before being put into official operation.
As of late June, 72.79 percent of the project's workload had been completed. The items of information, signals, and electricity supply for overhead stations has been wholly done.
MRB said during the interlocking commission phase, trains will be operated along the route in accordance with different operating modes. Corresponding to each speed range, specific inspection procedures for trains and other items of the project will be performed.
The urban metro railway line No.3, connecting Nhon and Hanoi Station, uses ten trains designed and manufactured by Alstom of France.
The project has an investment of about 30.1 trillion VND (1.29 billion USD) comes from official development assistance of the French Development Agency and loans from the French Government.
It will span 12.5km, running through six districts: Nam Tu Liem, Bac Tu Liem, Cau Giay, Ba Dinh, Dong Da and Hoan Kiem. It consists of 12 stations, including eight elevated and four underground./.
Six out of 10 trains were transported to the Nhon depot for pairing, calibrating and performing static and dynamic tests before being put into official operation ( |
The items of information, signals, and electricity supply for overhead stations has been wholly done (Photo: VNA) |
The project has an investment of about 30.1 trillion VND (1.29 billion USD) comes from official development assistance of the French Development Agency and loans from the French Government (Photo: VNA) |
Source: VNA
Ministry affirms Cat Linh-Ha Dong metro line certified as safe by French consultant
Responding to news about the recommendations from Apave-Certifier-Tricc (ACT), a French consulting firm, over the safety of the Cat Linh-Ha Dong urban railway project,