Recently, the Hanoi Urban Railway Management Board announced that the State Council for Construction Project Acceptance has conditionally approved the inspection results, agreeing to commence commercial operations of the elevated section of the Nhon-Hanoi metro line starting August 9.

W-metro Nhổn.jpg

On August 5, observations along the project route showed several trains conducting trial runs from Nhon depot to Cau Giay station.

W-1_metro Nhổn - ga Hà Nội .jpg

However, as of the afternoon of August 5, the exteriors of some stations along the line remained covered with tarps, and the surroundings appeared messy.

W-2_metro Nhổn - ga Hà Nội .jpg

At Station S01 - Nhon, the starting point of the line, the staircase handrails are still incomplete.

The area remains cluttered and dusty, with no workers in sight. Security cameras have been installed in some station pathways.

W-4_ga Nhổn.jpg

Given the current state, it's hard to believe the project will be operational in just three days.

W-5_metro Nhổn - ga Hà Nội .jpg

Despite sunny weather on the afternoon of August 5, rainwater remained stagnant at Nhon station from previous days.

W-6_metro Nhổn - ga Hà Nội .jpg

Currently, all eight elevated stations and the Nhon depot have received fire safety inspection approval.

At Station S8 - Cau Giay (the last station of the elevated section) on the afternoon of August 5, the access paths were littered with trash, and the elevators and escalators were covered with tarps to protect them from dust.

W-13_metro Nhổn - ga Hà Nội .jpg

After years of delays, the equipment and materials installed at the stations no longer appear new and have even become tarnished.

W-11_metro Nhổn.jpg

Inside the workshop area, workers are completing the sidewalks and roadbeds.

W-15_Khổ ray metro Nhổn - ga Hà Nội .jpg

The project uses a 1,435mm dual-gauge railway; European standard UIC 60 rails or equivalent. The train cars are medium-sized - type B (European standard) with a width of 2.7m and a total train length of 78.3m (four cars).

W-16_metro Nhổn - ga Hà Nội .jpg

Currently, the area where the track descends to the underground section beside Thu Le Lake is still cluttered with construction materials.

Inside Nhon station, as recorded by reporters nearly a month ago, the area appeared relatively clean.

tuyen metro nhon ga ha noi 884.jpg

The Nhon-Hanoi metro line has a total length of 12.5 km (8.5 km elevated and approximately 4 km underground).

Route: starting from Nhon - along National Highway 32 - Cau Dien - Mai Dich - intersection with Ring Road 3 - Cau Giay (intersection with Ring Road 2) - Kim Ma - Cat Linh - Quoc Tu Giam - ending at Hanoi Station (on Tran Hung Dao Street, in front of Hanoi Railway Station).

The project commenced in September 2010 with an initial completion target of 2016. After several delays, the new timeline for full operation is projected for 2027. The initial investment was 18 trillion VND, but it has nearly doubled to over 34.5 trillion VND (nearly $1.4 billion).

Pham Hai - Hoang Ha