Cost overruns in HCMC’s first metro project explained

In a report sent to the NA, the Government pointed out that the volatile exchange rate between the Vietnamese dong and the Japanese yen is one of the main reasons for cost overruns in HCMC’s Metro Line No.1 project.

Cost overruns in HCMC’s first metro project explained

An elevated section of HCMC’s Ben Thanh–Suoi Tien metro line runs along Hanoi Highway. The Government pointed out that the volatile exchange rate between the Vietnamese dong and the Japanese yen is one of the main reasons for cost overruns in HCMC’s Metro Line No.1 project - PHOTO: VNA

Vietnam typically takes out yen loans for projects funded by Japanese official development assistance (ODA). Therefore, any fluctuations of the Japanese currency would have immediate effect on yen loans for Vietnam.

In the report, the Government said that the surge in costs of the city's first metro line, which links Ben Thanh Market in District 1 and Suoi Tien Theme Park in District 9, resulted from price changes for materials and minimum wage hikes in the 2006-2009 period, VnEconomy news site reported.

The higher-than-expected costs were also blamed on the increasing workload to drive the project’s efficiency. In particular, the costs of equipment at stations and of carriages were increased to meet demand. Modern systems were purchased to ensure safety.

The third reason for the cost overruns was the fluctuating rate between the Japanese yen and the Vietnamese dong and backup costs, according to the report.

The total original investment for the project approved in 2007 was some 126 billion yen, or VND17.4 trillion. The recalculated cost soared to 236.6 billion yen, or VND47.3 trillion in 2011. In 2018, the Government reported this figure to the National Assembly.

Currently, the total investment capital for the project is estimated at 229.7 billion yen, or VND47.3 trillion, with 203.1 billion yen, or VND41.8 trillion, coming from yen loans funded by the Japanese Government and some VND5.5 trillion taken from the city’s budget.

 

To mobilize foreign capital for the project, the Ministry of Finance has signed three agreements to borrow 155.3 billion yen from the Japanese government.

The total disbursement for the project so far amounts to VND15.8 trillion, or 77.8 billion yen, making up 38% of the total ODA loans.

The HCMC government is in the process of completing procedures to have the adjusted plan passed.

Due to delays in site clearance and funding, the city’s first metro line is scheduled to be ready in the fourth quarter of 2021, instead of 2020. SGT

Hanoi’s first metro line begins 20-day trial run

Hanoi’s first metro line begins 20-day trial run

Hanoi's first metro project has started a 20-day trial run before being put into service officially.

Vietnam's Transport Ministry seeks to develop new metro lines

Vietnam's Transport Ministry seeks to develop new metro lines

The Ministry of Transport plans to develop 16 new metro line projects in HCMC and Hanoi, though the existing five projects are facing cost overruns and slow execution.

 
 

Other News

.
Vietnam promotes and protects human rights in Covid-19 epidemic
Vietnam promotes and protects human rights in Covid-19 epidemic
SOCIETYicon  27/12/2020 

The efforts of the Vietnamese Government during the Covid-19 epidemic is vivid evidence of the responsibility to protect and support vulnerable groups in the realization of human rights according to UPR recommendations.

A special flight to guarantee citizens' right to life
A special flight to guarantee citizens' right to life
SOCIETYicon  26/12/2020 

The campaign to move Vietnamese citizens out of Hubei (China), the world’s corona virus epicenter in early February is a proof of the policy of putting people in the highest position,

Building a specialized monitoring agency to increase effectiveness in ensuring the rights of ethnic minorities
Building a specialized monitoring agency to increase effectiveness in ensuring the rights of ethnic minorities
SOCIETYicon  28/12/2020 

It is necessary to have a specialized monitoring agency to ensure the rights of ethnic minorities. 

Law on Support for and Development of Ethnic Minorities and Mountainous Areas should be issued
Law on Support for and Development of Ethnic Minorities and Mountainous Areas should be issued
SOCIETYicon  27/12/2020 

It is necessary to pass the promulgation and implementation of the "Law on Support for and Development of Ethnic Minorities and Mountainous Areas" 

The government accepts economic damage to guarantee the right to health care for everyone
The government accepts economic damage to guarantee the right to health care for everyone
SOCIETYicon  27/12/2020 

Despite many difficulties, in order to protect people's health, the Government plans to both self produce and import Covid-19 vaccine in order to vaccinate every citizen.

Human rights viewed from illegal sales of personal information
Human rights viewed from illegal sales of personal information
SOCIETYicon  29/12/2020 

Illegally holding, trading, or transferring personal information of another person without authorization is infringement of privacy - one of the fundamental rights of human rights.

After 5 years, our country is really better, all people enjoy development results
After 5 years, our country is really better, all people enjoy development results
SOCIETYicon  27/12/2020 

After implementing the five-year social-economic development plan (2015-2020), the country’s situation is really better than ever, with high economic growth rate,

Human rights considerations: Dialogue and cooperation are the only effective way
Human rights considerations: Dialogue and cooperation are the only effective way
SOCIETYicon  27/12/2020 

Vietnam does not support resolutions on human rights in a particular country but believes that dialogue and cooperation are an effective way to consider human rights issues, not criticize each other or pressuring, politicizing human rights.

Resolution No. 28-NQ/TW: A progressive resolution promoting the right to social security
Resolution No. 28-NQ/TW: A progressive resolution promoting the right to social security
SOCIETYicon  27/12/2020 

Resolution No. 28-NQ/TW, issued on May 23, 2018 of the Party Central Committee, is considered to have the contents of reforming the social insurance policy progressively, 

Despite difficulties, Vietnam constantly promotes the right to social security
Despite difficulties, Vietnam constantly promotes the right to social security
SOCIETYicon  28/12/2020 

The 2013 Constitution of the State of Vietnam recognizes citizens' rights to social security in Article 34. Accordingly, citizens are ensured in terms of social welfare.

Accepting economic losses, protecting people's lives at all costs
Accepting economic losses, protecting people's lives at all costs
SOCIETYicon  28/12/2020 

On the basis of the humanistic point of view of "not letting anyone behind", by specific actions, ensuring human rights, the campaign against Covid-19 pandemic of Vietnam is an outstanding success, becoming a bright spot in the world.

Vietnam - a typical case of integrating human rights protection
Vietnam - a typical case of integrating human rights protection
SOCIETYicon  28/12/2020 

Chairman of the Mary Robison Foundation said that Vietnam is a typical case of integrating human rights issues, including the promotion of gender equality in climate change response policies.

Achievements in ensuring human rights, the premise for Vietnam’s positions at international forums
Achievements in ensuring human rights, the premise for Vietnam’s positions at international forums
SOCIETYicon  28/12/2020 

The outstanding results in the international arena, with the most typical one is being elected as the Non-Permanent Member of the United Nations Security Council, have confirmed the new stature of the Vietnamese State.

Ministry of Information and Communications strives to contribute to protecting children's rights in cyberspace
Ministry of Information and Communications strives to contribute to protecting children's rights in cyberspace
SOCIETYicon  28/12/2020 

Building a child protection network in the cyberspace will connect agencies, organizations and businesses together, forming a harmonious process to prevent, detect, intervene and handle acts of child abuse in the Internet environment.

Vietnam - a responsible member of international human rights conventions
Vietnam - a responsible member of international human rights conventions
SOCIETYicon  27/12/2020 

Through international cooperation activities on human rights, Vietnam has played an increasingly important role and actively contributed to the building of common values of human rights in the region and the world.

Efforts of the whole socio-political system to "Leaving no one behind"
Efforts of the whole socio-political system to "Leaving no one behind"
SOCIETYicon  29/12/2020 

For any political regime, social security in general, social insurance and health insurance policies in particular are also considered an important foundation for a country’s economic development and socio-political stability.

Vietnam listed among countries with high Human Development Index for the first time
Vietnam listed among countries with high Human Development Index for the first time
SOCIETYicon  29/12/2020 

Human rights or human development is a central issue in the development process in Vietnam. 

Human Rights achievements: Impressive communications from direct to online mode
Human Rights achievements: Impressive communications from direct to online mode
SOCIETYicon  27/12/2020 

In addition to communication methods such as writing articles, activities of agencies and organizations, the propaganda of human rights is also implemented through the organization of photo exhibitions and advanced IT applications.

Impressive model of friendly bookcase at Ngoc Ly detention center
Impressive model of friendly bookcase at Ngoc Ly detention center
SOCIETYicon  26/12/2020 

The fact has proven that converting and making changes in awareness is the best way of education. It will awaken the germ of goodness which is inherent and latent in each human being.

The role of journalists is indispensable for protection of human rights
The role of journalists is indispensable for protection of human rights
SOCIETYicon  26/12/2020 

The media plays the role of an essential means of communication in social life, the mouthpiece of the Party's agencies, the State, political and social organizations, the forum of the people.

 
 
 
Leave your comment on an article

OR QUICK LOGIN