Designed as a major urban arterial road, the boulevard will feature six main traffic lanes and up to four frontage road lanes.
Sections running close to the right-bank Red River dike will have a cross-sectional width of 54m, accommodating six main traffic lanes and two frontage road lanes on the riverside.
Sections farther from the dike will be 73.5m wide, with six main traffic lanes and four lanes on two frontage roads.
The section passing Long Bien Bridge will feature a partially underground design with a typical cross-sectional width of 66m, including six traffic lanes inside the tunnel and four lanes outside.
The boulevard will have eight grade-separated interchanges connecting with Hong Ha, Thuong Cat, Nhat Tan, Tu Lien, Chuong Duong, Thanh Tri, Ngoc Hoi and Me So bridges.
It will not connect directly with Thang Long, Long Bien, Tran Hung Dao or Vinh Tuy bridges.
The Hanoi People's Committee has assigned the Department of Construction to review and certify planning documents in accordance with the approval decision and lead studies to determine road boundaries at major intersections along the boulevard.
The Department of Agriculture and Environment will guide relevant agencies in ensuring compliance with flood prevention and dike safety requirements. Any necessary adjustments or additions to the plan must be submitted to competent authorities for consideration.
Authorities in the nine wards and communes along the route will be responsible for managing urban planning and architecture, issuing construction permits within their jurisdiction, addressing planning violations and incorporating the approved alignment into local planning documents.
Nearly 79km of boulevards along the Red River
The Right Bank Red River Scenic Boulevard forms part of a broader infrastructure project covering both banks of the river, with a combined length of approximately 79km.
The left-bank boulevard will stretch approximately 35.04km, starting at the intersection with Hong Ha Bridge in Me Linh Commune and ending at Hanoi's administrative boundary in Bat Trang Commune. It will pass through eight wards and communes.
The right-bank boulevard will extend approximately 44.3km, connecting Hong Ha Bridge in O Dien Commune with Me So Bridge in Hong Van Commune.
The respective route alignment plans were approved under Decisions No. 6380/QD-UBND and No. 6382/QD-UBND, both dated November 20, 2026.
Under Hanoi's approved plans, each boulevard will feature eight to 10 traffic lanes, including six main traffic lanes and two to four frontage road lanes, depending on the route's proximity to the dikes.
Each boulevard will have eight grade-separated interchanges. Both routes will connect with five bridges: Hong Ha, Thuong Cat, Nhat Tan, Tu Lien and Thanh Tri.
The two boulevards are among the infrastructure projects scheduled for implementation during the 2026-2030 period.
All 18 component projects under the Red River Scenic Boulevard development are expected to be fully completed by 2038.
Thanh Hue